SYSTEM  CHECK

Before Start-Up:

1.  All wiring should be in accordance with local    
 codes.
2.  Refrigerant lines should be properly sized.
3.  Thorough evacuation and dehydration has been 
 performed.
4.  The suction, discharge, and receiver service    
  valves must be open.

5.  The system preferably include a liquid line filter  

  drier moisture indicator and suction filter.

6.  Pour enough water into the drain pan to allow a  
  good check on drainage and seal the trap.

After Start-Up:

1. Check the oil level to be sure the oil charge is   
 correct.
2.  On initial start up the fans do not start until coil 
  temperature is pulled down to approximately 25°F 

 

  (-4°C) 

on the coil. Also, it is normal for the fan to  

  cycle a few times until the room temperature is  
  pulled down.
3.  If necessary, temporarily by-pass fan delay control  
  (to run fans until room temp is lowered).
4.  Be sure that the expansion valve is properly set to  
  provide the correct amount of superheat.
5.  After the box temperature is close to reaching the  
  desired temperature, the evaporator superheat  
  must be checked and adjustment made if  

 

 necessary. In general, evaporators running with  
  a TD of 10°F 

(5.6°C

 ) should have a superheat  

  reading of 6° to 8°F 

(3.3°C  to 4.4°C)

. For 

  evaporators with another T.D., the general rule is  
  that the superheat should be around 60 to 
  80% of T.D.
6.  Heavy moisture loads are usually encountered  

  when starting the system for the first time.  

 

  This may cause a rapid build-up of frost on the  
  evaporator. During the initial pull down, we 
  suggest that the frost build-up be watched and  
  defrosted manually as required. 
7.  Observe that the system goes through at least  
  one complete DEFROST CYCLE. 

PIPING

Refrigeration grade piping must be used for all field 

refrigeration piping. Refrigerant line sizes are important 
and 

may not

 be the same size as the coil connections. 

Consult ASHRAE handbook or other similar reference 
book for proper line sizing.
Refrigerant piping and control system should be designed 
to prevent possible liquid slugging (from oil or refrigerant) 
of the compressors on start-up after the defrost cycle. 
Also, it should prevent oil logging and minimize refrigerant 
pressure drop. 

WIRING

Wire system in accordance with governing standards and 
local codes. See data and wiring diagrams on pages 4 to 
20 for typical wiring arrangement. Electrical wiring is to be 
sized in accordance with minimum circuit ampacity rating 
(MCA).

 

Size fuses used must not exceed the Maximum 

Fuse Size ratings.

For ease of identifying the proper wiring terminal, unit 
wiring is color coded and terminal block connections are 

identified.

When 

fan delay thermostats 

(combination fan delay and 

defrost termination) are installed, on start-up, the fans 
do not operate until the coil temperature is reduced to 
approximately 25

o

F  

(-4°C)

. It is normal for the fans to 

cycle a few times until the room temperature is brought 
down. At higher evaporating temperatures this control 
may not close and therefore should either be by-passed 
temporarily or replaced with an adjustable type. (set for a 
higher temperature cut-in point). 

MAINTENANCE

The unit should be periodically inspected for any dirt or ice 

build-up on the fin surface and cleaned if necessary with 

a soft whisk or brush. Also ensure coils inner (and outer) 
drain pans do not have any ice build-up from improper 

defrost operation. When replacing heater elements first 

remove heater retainer brackets and heater clips. 

INSTALLATION INSTRUCTIONS

TPLP

60Hz

23/12/16

T30-TPLP-PDI-11

- 25 -

Содержание TPLP Series

Страница 1: ...2 Recommended Expansion Valve Selections 23 Installation Instructions 24 25 Generic Service Parts 26 Warranty 27 Project Information 27 As Built Service Parts Back Questions about this product Email e...

Страница 2: ...s approximate 3 4 ID Universal drain fitting for 3 4 MPT or 3 4 flare fitting Factory installed distributor nozzle 460 1 60 PSC motor only EC motors with patented SmartSpeed Technology See page 16 Hea...

Страница 3: ...MBLED FEATURES Schrader Valve Located Outside Solenoid Valve Wire pulled through and labeled on each end Solenoid Valve and TXV Mounted Thermostat Mounted on Front of Unit 60Hz TPLP 23 12 16 T30 TPLP...

Страница 4: ...7 8 3 5 R407C R404A R507 R22 R134a 0 99 0 92 0 93 1 02 1 03 Low Temperature Models Capacity 6 F P I Low Temp Models 104L 105L 106L 207L 209L 211L 314L 317L 419L 422L 527L 631L Number Of Fans 1 1 1 2 2...

Страница 5: ...ACITY A MAX FUSE AMPS HP FLA TOTAL WATTS MIN CIRC AMPACITY A MAX FUSE AMPS 104MAS2 6 1 1 15 0 5 100 0 6 15 1 15 0 6 60 0 8 15 106MAS2 1 1 15 0 5 100 0 6 15 1 15 0 6 60 0 8 15 107MAS2 1 1 15 0 5 100 0...

Страница 6: ...200 1 1 15 1 15 1 2 120 1 4 15 1890 8 2 10 3 15 5 3 6 7 15 209LE 2 1 15 1 0 200 1 1 15 1 15 1 2 120 1 4 15 1890 8 2 10 3 15 5 3 6 7 15 211LE 2 1 15 1 0 200 1 1 15 1 15 1 2 120 1 4 15 1890 8 2 10 3 15...

Страница 7: ...4 1 5 1 15 209LES4 2 1 15 0 8 200 0 9 15 1890 4 1 5 1 15 211LES4 2 1 15 0 8 200 0 9 15 1890 4 1 5 1 15 314LES4 3 1 15 1 2 300 1 3 15 2730 5 9 7 4 15 317LES4 3 1 15 1 2 300 1 3 15 2730 5 9 7 4 15 419L...

Страница 8: ...ORATOR NAMEPLATE FOR ELECTRICAL L1 PARAGON 8145 DEFROST CLOCK OR EQUIVALENT THERMOSTAT CIRCUIT FUSE OR NOTE 3 BREAKER SWITCH PUMP DOWN IF USED NOTE 4 SPACE LIQUID LINE SOLENOID VALVE NOTE 4 N C WITH D...

Страница 9: ...VALENT THERMOSTAT CIRCUIT FUSE OR NOTE 3 BREAKER SWITCH PUMP DOWN IF USED NOTE 4 SPACE LIQUID LINE SOLENOID VALVE NOTE 4 N C WITH DEFROST TIME CLOCK 380 400 1 50Hz CONTROL VOLTAGE GND L1 GND IF N 2ND...

Страница 10: ...3 DEFROST CLOCK PARAGON 8145 EVAPORATOR OPTIONAL FACTORY FACTORY WIRING WIRING BY OTHERS ALL FIELD WIRING MUST BE DONE IN COMPLIANCE WITH ALL APPLICABLE LOCAL AND NATIONAL CODES 2 LP ED 12 07 TERMINAL...

Страница 11: ...CE WITH ALL APPLICABLE LOCAL AND NATIONAL CODES 3 LP ED CONTACTOR SINGLE 12 07 TERMINAL BLOCK TERMINAL COMPONENT TERMINAL CONDUCTORS WIRING TERMINALS NOTE 4 SOL VALVE N C LIQUID LINE OR BY OTHERS AND...

Страница 12: ...WITH ALL APPLICABLE LOCAL AND NATIONAL CODES 3A LP ED 3ph CONTACTOR SINGLE 12 07 TERMINAL BLOCK TERMINAL COMPONENT TERMINAL CONDUCTORS WIRING TERMINALS NOTE 4 SOL VALVE N C LIQUID LINE OR BY OTHERS AN...

Страница 13: ...K PARAGON 8145 EVAPORATOR OPTIONAL FACTORY FACTORY WIRING WIRING BY OTHERS ALL FIELD WIRING MUST BE DONE IN COMPLIANCE WITH ALL APPLICABLE LOCAL AND NATIONAL CODES 7 LP ED CONTACTOR SINGLE 12 07 TERMI...

Страница 14: ...P ED CONTACTOR MULTI 12 07 TERMINAL BLOCK TERMINAL COMPONENT TERMINAL CONDUCTORS WIRING TERMINALS DATA PLATE FOR MOTOR QUANTITY EVAPORATOR REFER TO POWER PLUGS FAN MOTOR H2 NOTE 4 SOL VALVE L2 L1 N C...

Страница 15: ...MINAL CONDUCTORS WIRING TERMINALS DATA PLATE FOR MOTOR QUANTITY EVAPORATOR REFER TO POWER PLUGS FAN MOTOR NOTE 4 SOL VALVE L2 L1 N C LIQUID LINE L2 T2 L1 C T1 GND OR BY OTHERS AND WIRED ON EVAPORATOR...

Страница 16: ...talled thermostat a field wired SPDT type thermostat is required 0 2000 4000 6000 8000 10000 12000 14000 16000 18000 20000 0 50 100 150 200 250 300 350 400 450 500 Energy Consumption Watt Hours Time m...

Страница 17: ...WIRING DIAGRAM 115 1 60 208 230 1 60 OPTIONAL EC MOTORS with AIR DEFROST MODELS TPLP ECM 60Hz 23 12 16 T30 TPLP PDI 11 17...

Страница 18: ...WIRING DIAGRAM 208 230 1 60 OPTIONAL EC MOTORS with ELECTRIC DEFROST MODELS TPLP ECM 60Hz 23 12 16 T30 TPLP PDI 11 18...

Страница 19: ...WIRING DIAGRAM 208 230 1 60 OPTIONAL EC MOTORS with ELECTRIC DEFROST MODELS MULTIPLE EVAPORATORS TPLP ECM 60Hz 23 12 16 T30 TPLP PDI 11 19...

Страница 20: ...4 639MA 192 87 Electric Defrost Models MODEL NUMBER SHIPPING WEIGHT LB kg 104ME 104LE 103VE 49 22 106ME 105LE 104VE 51 23 107ME 106LE 105VE 53 24 209ME 207LE 206VE 76 34 211ME 209LE 208VE 80 36 214ME...

Страница 21: ...1 N A N A 1 1 8 3 8 3 8 419L 4 78 1 4 1988 32 5 8 829 32 5 8 829 1 1 8 3 8 3 8 422L 4 78 1 4 1988 32 5 8 829 32 5 8 829 1 1 8 3 8 3 8 527L 5 94 1 4 2394 32 5 8 829 48 5 8 1235 1 3 8 3 8 1 2 631L 6 110...

Страница 22: ...407C R22 R134a 104M N A EBQE AA C EBQE AAA VC EBQE AAA JC 106M L 1 2 EBQE AA C EBQE AA VC EBQE AA JC 107M L 1 2 EBQE A C EBQE AA VC EBQE AA JC 209M L 3 4 EBQE A C EBQE AA VC EBQE AA JC 211M L 1 EBQE A...

Страница 23: ...6V L 2 1 2 EBQE A VC EBQE B VZP40 EBQE B VZP40 EBQE B VZP40 EBQE B VZP40 419V G 3 EBQE A VC EBQE B VZP40 EBQE B VZP40 EBQE B VZP40 EBQE B VZP40 523V G 4 EBQE B VC EBQE B VZP40 EBQE C VZP40 EBQE C VZP4...

Страница 24: ...ion should be given to the coil location in order to minimize the piping run length to the condensing unit and floor drain EXPANSION VALVE TXV PRE SELECTED Locate the expansion valve bulb on a horizon...

Страница 25: ...YCLE PIPING Refrigeration grade piping must be used for all field refrigeration piping Refrigerant line sizes are important and may not be the same size as the coil connections Consult ASHRAE handbook...

Страница 26: ...SERVICE PARTS TPLP 60Hz FOR SERVICE PARTS LOOK UP visit http www t rp com serv_parts htm email parts t rp com call 1 844 893 3222 x501 23 12 16 T30 TPLP PDI 11 26...

Страница 27: ...duct in a corrosive atmosphere c damages caused by any unauthorized alteration or repair of the system affecting the product s reliability or performance d damages caused by improper matching or appli...

Страница 28: ...ION AIR CONDITIONING CANADA CORP 159 Roy Blvd Brantford Ontario Canada N3R 7K1 PHONE 519 751 0444 800 463 9517 FAX 519 753 1140 www t rp com Due to National Refrigeration s policy of continuous produc...