24
Evaporator Piping
1.
Install the TXV directly to the unit liquid connection.
2.
Locate the TXV bulb midway between the 90 degrees
bends on top of the suction line as illustrated in Figure
3-7A.
3.
Secure the bulb to the suction line with two clamps pro-
vided by the manufacturer and insulate the bulb.
4.
Install the Frostat
TM
according to the instructions en-
closed in the kit as close to the evaporator as possible.
Figure 3-7A
Typical Coil Piping For Dual Circuit Units
Hot Gas Bypass for Commercial Comfort-
Cooling Applications
Hot gas bypass is not recommended for use on RAUC
units. Frostat
TM
is the preferred method of protecting the
evaporator from freeze-up. It turns off compressors when
the coil frosting is sensed. The compressor is allowed to
operate when the coil temperature rises a few degrees
above the frosting condition. This action reduces the over-
all energy consumption of the system while reliably main-
taining system control.
For more information, refer to the latest edition of Applica-
tion Guide SS-APG001-EN.
Optional Pressure Gauges
When a unit is ordered with optional pressure gauges, (“F”
in the miscellaneous digit of the model number), a set of
gauges and the necessary mounting hardware ship in the
location illustrated in the Unit Component “Layout” and
“Shipwith” Location. The mounting location and tubing con-
figuration for the optional pressure gauges after field instal-
lation is shown below.
1. Assemble the valve depressor, flare nuts, 1/4" copper
tubing, 90 degree flare elbows, gauge & gauge bracket
together as shown in Detail “A” & “B”.
Note: Wrap all appropriate pipe threads with teflon
tape before assembly.
Installation (Continued)
Содержание RAUC-IOM-15
Страница 8: ...8 Figure 3 2A RAUC C80 Unit Dimensional Data Recommended Clearances...
Страница 9: ...9 Figure 3 2A Continued RAUC D10 Unit Dimensional Data Recommended Clearances...
Страница 10: ...10 Figure 3 2A Continued RAUC D12 Unit Dimensional Data Recommended Clearances...
Страница 11: ...11 Figure 3 2B EVPB C80 Evaporator Chiller Dimensions...
Страница 12: ...12 Figure 3 2B Continued EVPB D10 Evaporator Chiller Dimensions...
Страница 13: ...13 Figure 3 2B Continued EVPB D12 Evaporator Chiller Dimensions...
Страница 14: ...14 Figure 3 2B Continued EVPB C80 through D12 Chill Water Pipe Stubout Dimensions...
Страница 35: ...35 Installation Continued Field Connection Diagram Notes for all System Control Options...
Страница 57: ...57 Figure 5 5 Typical Scroll Compressor Terminal Block System Start Up Continued...
Страница 67: ...67...
Страница 68: ...68...