TRAK Machine Tools

 

Site Preparation Guide 
TRAK DPMRX3 

                                                                                                                                               F16467-45 Rev 020921 

Page 3 of 4 

Lifting and/or Moving the Machine 

 

Method 1 (see Figure 1): 

 

1.

 

 Insert a steel bar 1.0" dia x 36" long through the rear 

side holes of the bed (under column).   

2.

 

 Use a steel cable (with protective covering) min. 3/4" dia. 
or a 3 ton sling. 

3.

 

 Use cardboard pieces or other suitable protective sheets 
on both sides of the machine to prevent scratching. 

4.

 

Remove the 4 nuts and screws holding the machine to the 
wood skid. 

5.

 

Lift the machine (the front side of the machine should be 

lower than the back side). 

6.

 

Insert the 6 screws for leveling pads in their place in the 

bed.  

7.

 

Place the machine in its location (see floor plan and bed 

footprint drawing) carefully positioning each leveling pad 
under each leveling screw. 

8.

 

 Remove the lifting cable or sling, the steel bar and all 

protective cardboard. 

CAUTION! 

The DPMRX3 machine weighs approximately 4100 
lbs. Proper equipment of sufficient capacity must 

be used when lifting and/or moving the machine. 

Figure 1 Lifting the Machine Method 1

 

 