3. From the PathPilot interface, on the
Settings
tab, select the
ATC
radio button.
Figure 2-39: ATC radio button on the Settings tab.
The
ATC
tab appears in the PathPilot interface.
Note:
If prompted, you may need to update the
firmware for the ATC. Follow the on-screen
instructions.
4. Load a tool into the spindle:
a. Push and hold the collet open button on the side of the
ATC.
Figure 2-40: Collet open button on the side of the ATC.
The collet opens.
b. Load a tool into the spindle.
c. Release the button.
The collet closes.
5. From the PathPilot interface, on the
Main
tab, in the
RPM
DRO field, type
1000
. Then select the
Enter
key.
6. Select
FWD
.
The spindle starts.
7. From the
Status
tab, make sure that the
VFD Running
green
light comes on.
Figure 2-41: VFD Running light on the Status tab.
Note:
If the VFD Running light did not come on in the
previous step, we can help. Email
[email protected] to contact Tormach Technical
Support for guidance on how to proceed.
8. Select
Stop
.
The spindle stops.
Adjust the Power Drawbar
If you have not yet done so, you must adjust the Power Drawbar.
Complete the following steps in the order listed:
Adjust the Drawbar Tension
This adjustment sets the highest possible drawbar tension while
still allowing the Power Drawbar cylinder to release the tool. For
information, see "About Drawbar Tension" (on the next page).
NOTICE!
After the initial installation, you must examine the
drawbar tension weekly. During periods of heavy use, examine
the drawbar tension more frequently. If you don't, there's a
risk of tool pull-out.
To adjust the drawbar tension:
1. Put an empty Tormach Tooling System (TTS) tool holder into
the collet.
2. While using one hand to support the tool holder, use the other
to push the Release Tool button.
Page 14
©Tormach® 2019
Specifications subject to change without notice.
tormach.com
TD10559: Owner's Guide: M ATC Retrofit for PCNC 1100 Series 3 (1119A)
TECHNICAL DOCUMENT