172-65254M-03 (A-COS-10) 27 Oct 2008
8
Installation
Install properly and DO NOT use this product outside the recommended
operating pressure, temperature and other specification ranges.
Improper use may result in such hazards as damage to the product or
malfunctions which may lead to serious accidents. Local regulations
may restrict the use of this product to below the conditions quoted.
CAUTION
Use hoisting equipment for heavy objects (weighing approximately
20 kg or more). Failure to do so may result in back strain or other injury if
the object should fall.
CAUTION
Take measures to prevent people from coming into direct contact with
product outlets. Failure to do so may result in burns or other injury from
the discharge of fluids.
CAUTION
Installation, inspection, maintenance, repairs, disassembly, adjustment and valve
opening/closing should be carried out only by trained maintenance personnel.
1. Blowdown
Before installing the
COSPECT
unit, be
sure to blow down all piping thoroughly. If
this is not possible, perform a blowdown
using the bypass valve.
Blowdown is especially important for
newly installed piping or after the system
has been shut down for a long period of
time.
2. Removing Seal and Cap
Before installation, be sure to remove all protective seals and caps.
(Found in 3 locations, on the product inlet and outlets.)
3.
Installation Angle
Install the
COSPECT
vertically, so that the arrow
mark on the body points horizontally in the direction
of air flow.
Allowable inclination is 10 degrees in the fore-aft
direction and 15 degrees in the plane perpendicular
to the air flow line.
4.
Spacer Installation
If spacing adjustment is necessary
to accommodate installation,
install a spacer on the outlet
flange. The spacer should consist
of a spacer, gaskets, bolts and
nuts. Fit gaskets to both sides of
the spacer between the
COSPECT
outlet and the pipe flange. Fasten
with bolts and nuts.
Correct Spacer
Location
Incorrect Spacer
Location
Blowdown Using
Bypass Valve
Blowdown
Piping Before
Installation