14
Installation of ODU
Handling
Notes:
●
Fragile and handle with care.
●
The degree of inclination shall not exceed 30° while handling (do not put the unit on
its side).
●
Keep heat exchange fins safe while handling and installing the unit. In case of any
damages, please use fin comb to fix it up.
●
Properly dispose of packaging bags and prevent kids from playing with them.
Hook
Hoisting rope
Protective pad
Lifting hole (two at the front
and two at the back)
Keep the ropes through the
holes to ensure stability
during hoisting.
Forklift pocket
● Use forklift to handle: be careful when inserting the fork into the pocket at the bottom,
and prevent fork from damaging the unit or the unit bottom.
●
Use crane to handle: tighten hoisting rope according to what is shown in the figure,
and keep the unit weight even during hoisting.
●
Use two hoisting ropes at least 8 m long and about 20 mm in diameter to support the
unit weight. Do not use tying band of the unit for handling.
●
After the wooden framework is removed: use paper or cloth as pad between hoisting
rope and the unit to prevent damages to the unit body.
Placement
●
Make sure the ODU is placed firmly at a level place to prevent vibration and noises.
●
Use a base larger than the width of ODU's support legs (66 mm) to support the unit.
●
The shock-absorbing pads shall cover the entire bearing surface of the base.
●
The unit base shall be at least 200 mm higher above the ground.
●
Around the base there should be drain to ensure that the condensate water
generated during operation could flow out.
Содержание TIMS-X Series
Страница 1: ...INVERTER MULTI SYSTEM UNIT Applicable to TIMS X XA XT C series https tica pro...
Страница 27: ...27 Installation of Refrigerant Piping TBP4033TA TBP4072TA...
Страница 28: ...28 Installation of Refrigerant piping TBP4073TA Qty 2 Qty 2...
Страница 29: ...29 TBP4090TA...
Страница 30: ...30 TBP4135TA Qty 2 Qty 2...
Страница 57: ...141014 12 805 7 495 127 79 00 7 969 190 85 85 Email info tica pro...