NORMAL SEQUENCE OF OPERATION
Limits and operating controls such as safety and operating temperature limits,
water flow switch, thermal fuse switches and high/low gas pressure switch
contacts must be closed to initiate and continue burner sequence. Flame
signal must not be present. Airflow switch must be open.
Control terminal 5 is energized and all safety and operating control contacts
are closed. Control terminal 4 is energized to start the combustion air fan.
Contacts close when fan generates enough differential air pressure to actuate
combustion air flow switch diaphragm.
Fan purges combustion chamber and venting for 30 seconds.
Pilot gas valve(s) and ignition transformer are energized. Pilot gas flows to
pilot burner and is ignited.
Ignition transformer is de-energized after 5 seconds. Presence of pilot flame
is detected by ultraviolet scanner. Flame signal exceeds 1.5 volts DC.
Main gas valves are energized. Gas flows to main burner and is ignited by
pilot flame. Pilot and main flames are detected by ultraviolet scanner. Flame
signal continues to maintain 1.5 to 5.0 volts DC.
After 5 seconds, pilot gas valve(s) is de-energized. Gas flow to pilot stops.
Pilot flame is extinguished. Main flame is detected by ultraviolet scanner.
Flame signal continues to maintain 1.5 to 5.0 volts DC.
Main burner continues to operate until call for heat ends, contacts of a
safety or operating control open, electrical power is interrupted, or the flame
signal drops below 1.5 volts DC. Modulating water heaters operate based
on the load, determined by the difference between the bulk appliance water
temperature and the water set point.
Main gas valves are de-energized. Gas flow to main burner stops. Main
flame is extinguished. Fan continues to operate for 60 seconds to evacuate
combustion chamber and venting.
Water Heater in Standby
Call for Heat
Combustion Air Flow Switch
Contacts Make
Pilot Flame Establishing
Period Begins
Early Spark Termination
Main Flame Establishing
Period Begins
Run Period Begins
Run Period
Post Purge
Standby
30 sec.
5 sec.
5 sec.
3 sec.
Prepurge Begins
After 60 seconds fan stops.
Содержание EVA-1000
Страница 13: ...13 Figure 3 Sidewall Pressurized Venting Optional Figure 2 Sidewall Pressurized Venting...
Страница 14: ...14 Figure 4 Vertical Pressurized Venting...
Страница 16: ...16 Figure 7 Vertical Air Intake Piping...
Страница 26: ...26 Figure 9a Standard UL FM CSD 1 Wiring Diagram On Off...
Страница 27: ...27 Figure 9b Standard UL FM CSD 1 Wiring Diagram Modulation...
Страница 30: ...30 Figure 11 Modular System Horizontal Air Intake Piping...
Страница 31: ...31 Figure 12 Modular System Vertical Air Intake Piping...
Страница 46: ...46 This Page is Deliberately Left Blank...
Страница 47: ...47 Troubleshooting Guide...
Страница 48: ...48 Troubleshooting Guide...
Страница 51: ...51 Figure 19 Combustion Chamber Assembly...
Страница 53: ...53 Figure 20 Burner Assembly FRONT VIEW TOP VIEW...
Страница 55: ...55 Figure 21c UL FM CSD 1 Main Gas Train Assembly On Off Modulation...
Страница 57: ...57 Figure 22a DB B w POC Gas Train On Off 500 750 Figure 22b DB B w POC Gas Train On Off 1000 2000...
Страница 59: ...59 Figure 24b DB B w POC Gas Train Modulation 1000 2000 Figure 24a DB B w POC Gas Train Modulation 500 750...
Страница 61: ...61 Figure 25 Jacket Panels Indoor Units 4D 4J 4C 4B 4F 4I 4G 4E 4R 4K 4H 4J 4N 4M 4L 4Q 4A 4P 4P...
Страница 63: ...63 Figure 26a Control Panel Assembly On Off...
Страница 65: ...65 Figure 26b Control Panel Assembly Modulation...
Страница 67: ...67 Figure 27 Bishop Pilot Assembly...
Страница 71: ...71 NOTES...
Страница 72: ...72 NOTES...
Страница 73: ...73 NOTES...