Edition:10/14
13
Manual Storage Heater TTS with electronic control
GB
System Start-up
Note: The heaters are fed from three circuits: (1) the element feed, (2) the charge
control and (3) the discharge control circuit. All breakers must be off for the
heater to be safely de-energized to permit safe servicing.
Steps to activate the system
1.
Control Panel
- Energize control panel at the circuit breaker.
2.
Fans and Thermostats
- Check proper operation of fans and thermostats. Check to see
that the fans go ON and OFF with operation of the thermostat.
3.
Circuit Breakers
- Switch "ON" all element feed circuit breakers.
4.
Time Synchronization
- Check the synchronization of the control panel or time clock to
have it coincide with the time of day meter (see specific control panel instructions for
further information).
5.
First Charge
- The heater insulation is free from organic binding material. It can thus be
operated immediately without having to go on full charge in order to purge any odours. It
is, however, advisable, to ventilate the room well during the initial charging phase.
6.
Current Draw
- It is wise to check the current draw of each heater. See the Technical
Data Sheet for the proper amperage. This can be done at the breaker panel or at the
individual heaters.
Room Thermostat
The room thermostat must be installed according to national and local codes of practice. It
must also be earthed.
It is very important that the room thermostat be correctly positioned on the wall.
•
Air must be able to circulate freely around the thermostat.
•
The thermostat must be protected from direct sunshine and/or draughts.
•
Fix the thermostat to an inside wall opposite the heater itself (the ideal position is next to
the door).