18
www.tcsmeters.com
Total Control Systems
TCS 3000 Installation
Installation Procedure — LPG 1
-
Stage Security Valve
Installation Procedure:
1.
Using the bolts and gasket provided, install the 757 LPG valve on the outlet (downstream) side of the meter.
2.
Follow the instructions provided with the valve for wiring the solenoid.
3.
Mount the 3 Way Valve and threaded fitting directly to the TCS 3000 register and follow the instructions provided
with the Valve
.
*Note: Use Correct Thread Sealant*
4.
Once the solenoid is wired, run the corresponding wire as pictured using a minimum of 18 gauge shielded cable
into the back of the TCS 3000 register. The 3 Way valve will be wired into Solenoid 2 on the terminal board.
5.
TCS 3000 register product programming for Valve Type should be set to Single Stage.
*When Calibrating the Unit Set Up Valve Type as 1001*
GREEN
BLACK
BLACK
S2 – Fast Flow
Solenoid Valve