TCS 3000 Installation
Installation Procedure — 1
-
Stage Security Valve
Installation Procedure:
1.
Using the bolts and gasket provided, install the 655 Diaphragm or
755 Piston Valve on the outlet (downstream) side of the meter.
2.
Wire the solenoid valve to Solenoid 2 (S2) for a Single Stage oper-
ation
3.
Once the solenoid is wired, run the corresponding wire as pic-
tured using a minimum of 18 gauge shielded cable into the back
of the TCS 3000 register.
4.
Insert the solenoid wiring into the cable gland. Wire the solenoid
into the correct solenoid location on the terminal board. Leave a
small amount of slack on the wiring.
5.
Compress the cable gland on the TCS3000 register until it is snug
on the solenoid wire.
655
-
21 Diaphragm 2” Valve
755
-
21 Piston 2” Valve
755
-
31 Diaphragm 3” Valve
*When Calibrating the Unit Set Up Valve Type as 1101*
S2
S2
S2