MB2000/3000/5000 OPERATING AND MAINTENANCE MANUAL

 

  TAYLOR-WHARTON (BEIJING) CRYOGENIC EQUIPMENT CO., LTD.

                                 

 

10 

EQUALIZATION VALVE

HV10

 

To balance the pressure of liquid phase and gas phase ,the NI will be zero 
when it is opened.   

VACUUM PUMP 
DOWNCONNECTION 

PSE3

 

the port used to pump air from the tank insulation space. It is normally 
blanked-off and never opened uLI1ess the tank requires a field 
re-evacuation after a repair

 

VACUUM PROBE VALVE

HV8

 

a thermocouple that is installed to allow connection of a vacuum gauge to 
measure the quality of the vacuum in the insulation space

 

VACUUM PROBE

VJ

 

opened during vacuum measurement to expose the vacuum probe sensors to 
the tank insulation space

 

FILL LINE PURGE VALVE

HV17

 

used to vent the fill line during fill hose cool-down, and to drain liquid 
product trapped between the fill connection and the fill valves after a fill is 
completed

 

ATMOSPHERIC VAPORISER

E100

 

One heat exchanger that absorbs heat energy of around atmosphere and 
make the liquid vaporize gas . 

 
 

 

INSTALLATION 

 

HANDLING

 

 

Dimension and connection data for the MB tanks can be found on additional copies of these drawings 
may be requested from the factory. Please include information on the tank model number and part number 
in making requests for this drawing. The drawing part number is listed in the applicable Specification 
chart in this manual.   

Tank installation is the customer's responsibility. The MB tank with pallet for equipment to hand or transit 
expediently .no especial demand for the toft to use temporarily, advise build one toft for fixation long 
time ,and refer to local codes for recommended foundation specifications. Employ experienced personnel 
to move and install the tank. This tank must be shipped and lifted empty, and with a warm inner vessel

 

The tank can be used forklift handing or crane lifting bases on local condition . 

INSTALLATION CHECKS 

 

Before off-loading the tank, inspect it carefully for possible shipping damage. Report any damage to the 
carrier and the factory. In addition, check tank pressure and vacuum as follows:   

1. Tanks are shipped pressurized with nitrogen gas at about 0.175MPa. Open the gauge vapor phase 
isolation valve (RS) and read tank pressure indicated on pressure gauge or a pressure gauge installed by 
user. Record the "as received" tank pressure. close the vapor phase isolation valve.   

 

Tank pressure may change due to temperature variations, accidental opening of valves, packing leaks, 

or minor leaks at the fill connection. If a positive pressure is not indicated on the pressure gauge and no 
repairable leaks are found, contact the factory in accordance with conditions specified in the tank 
warranty.  

 

 

2. Check insulation space vacuum by connecting a Hasting-Raydist Model TV-4A or VT-6 vacuum gauge 
to the tank vacuum probe. Open the tank vacuum probe isolation valve, wait 60 minutes, and take a 
reading. If the "as received" vacuum (tank at ambient temperature) is greater than 2 Pa (0.02 mm Hg) 
absolute, contact the factory.   

 

 

Содержание M2000

Страница 1: ...NIC LIQUIFIED GAS TANK M2000 M3000 M5000 V2000 V3000 V5000 MB TANK VESSEL ON SKID FOR AIR LIQUIDE Taylor Wharton Beijing Cryogenic Equipment Co Ltd East End of Ping An Street Xianghe Economic Developm...

Страница 2: ...ON HANDLING 10 INSTALLATION CHECKS 10 OPERATION PURGE PROCEDURE 12 FILLING A WARM TANK 13 FILLING A COLD TANK 13 NORMAL OPERATION 14 TAKING A TANK OUT OF SERVICE 14 MAINTENANCE GENERAL 15 LEAK TESTING...

Страница 3: ...MAINTENANCE PROCEDURES READ AND FOLLOW ALL SAFETY PRECAUTIONS IN THIS SECTION AND IN REFERENCE PUBLICATIONS FAILURE TO OBSERVE ALL SAFETY PRECAUTIONS CAN RESULT IN PROPERTY DAMAGE PERSONAL INJURY OR P...

Страница 4: ...surfaces Equipment to be used in contact with liquid oxygen should be handled oLI1y with clean gloves or hands washed clean of oil Maintain Adequate Ventilation Enclosed areas containing oxygen equipm...

Страница 5: ...ygen systems on industrial and institutional consumer premises CAUTION When installing field fabricated piping make certain a suitable safety valve is installed in each section of piping between shut...

Страница 6: ...nd non flammable it can cause asphyxiation in a confined area without adequate ventilation Any atmosphere which does not contain enough oxygen for breathing can cause dizziness unconsciousness or even...

Страница 7: ...000 model cryogenic storage tanks These tanks are suitable for the storage and delivery of liquid oxygen nitrogen or argon at a maximum allowable working pressure of 1 6 MPa 232 psig for M series MB t...

Страница 8: ...RIES TANK MODEL Gross Volume m 3 Net Volume m3 Height m Dime nsions mm Weight Ton Full Weight Ton STATIC EVAPORATION LIN volume day MAWP MPa LOX LIN LAr M5000 4 99 4 49 3 2000 2 8 7 93 6 43 9 06 1 1 6...

Страница 9: ...MB2000 3000 5000 OPERATING AND MAINTENANCE MANUAL TAYLOR WHARTON BEIJING CRYOGENIC EQUIPMENT CO LTD 8...

Страница 10: ...SSURE BUILD UP VALVE HV3 It lets the liquid of the container flow to the build up pressure line when it is opened PRESSURE REGULATOR PCV1 When tank pressure decreases to PCV1 set point it opens and li...

Страница 11: ...stomer s responsibility The MB tank with pallet for equipment to hand or transit expediently no especial demand for the toft to use temporarily advise build one toft for fixation long time and refer t...

Страница 12: ...MB2000 3000 5000 OPERATING AND MAINTENANCE MANUAL TAYLOR WHARTON BEIJING CRYOGENIC EQUIPMENT CO LTD 11...

Страница 13: ...must be gradual enough to allow the liquid to vaporize in the bottom fill line and pressure building coil so the pressure builds up in the inner vessel Momentarily open top fill valve HV2 to flood the...

Страница 14: ...ts from tank trycock valve close supply source valve to stop fill Close tank trycock valve 8 When residual liquid in the fill hose vaporizes close tank top fill valve CAUTION To avoid injury do not to...

Страница 15: ...A TANK OUT OF SERVICE Schedule shut down operation to coincide with low liquid level in the tank If a large quantity of liquid is in the tank drain it into a trailer for use elsewhere or for disposal...

Страница 16: ...eaned for in conformance with CGA Pamphlet G 4 1 Cleaning Equipment for Oxygen Service or other equivalent standard If parts are purchased cleaned for oxygen service they should be suitably packaged t...

Страница 17: ...be set so that tank pressure is held about 0 035MPa above the desired delivery pressure the economizer pressure regulator PCV2 should be set at least 0 07MPa 10 psig above the setting of the pressure...

Страница 18: ...row away type PRESSURE AND LIQUID LEVEL GAUGES The major cause of malfunctioning tank pressure gauge inner vessel or liquid level gauge is an open equalization valve or leakage in the gauge lines Refe...

Страница 19: ...the vacuum probe into vacuum probe isolation valve using two wrenches Do not over tighten 5 Install a new vinyl cover over the vacuum probe connector NOTE If corrosion of the vacuum probe is a proble...

Страница 20: ...wn connection and vacuum bursting disc f All liquid and gas phase lines exit points through vacuum jacket g Any area of the vacuum jacket that might have been exposed to cryogenic liquid spray or temp...

Страница 21: ...ck d Liquid Level Gauge needle not zero adjusted e Gauge line reversed f Liquid Level Gauge damaged or faulty g Plugged gauge lines Test and repair leaks Close by pass valve Tap Liquid Level Gauge sli...

Отзывы: