Tanpera TDB Series Скачать руководство пользователя страница 12

Never fix the unit to its place by welding!

If the product is to be out of operation for a long time, drain the water and take precautions 

against freezing.

6.4.    

Installing the pipe connections

TANPERA storage water heaters and hot water storage tanks will be provided with internal thread 

connection ports.

We advise you of the following:

Pipe connections must be made according to an approved installation project.

Risk of fire!  The unit should not be approached with fire and any necessary precautions should 

be taken in the event of welding.  The insulation material and the sheath on the tank may burn.

There should be no shut-off valve between the safety valve and the tank, drain port of the valve 

should not be blocked in any way and the drain piping should be downward inclined and as short 

as possible.

9

 

We reserve the right to make changes in technical information.

Storage:

Should it be necessary to store the product for a longer period without installing, it should be stored 

in upright position on the pallet with original packaging, in a closed place, which is absolutely free of 

external weather conditions.

Rising of the unit:

The pallet should be removed before

 

mounting. 

To remove the pallet, lay down the unit on the 

ground, holding the 

eyebolts

 with the straps.

 

When doing this, take maximum care to ensure 

that the vinyl sheath does not tear 

(or the steel sheet sleeve does not deform).
Remove all tightening elements from the pallet.
Place the unit in its position on the floor, by 

holding from the 

eyebolts

 with the straps 

and

  bringing it back to the vertical position and 

lowering it on the legs.

Remove the straps, refit the thermoplastic cap and tighten the unit to the floor/pedestal using 

the mounting holes on the feet.

When connecting the pipe system to the product make sure that no stress or strain is imposed,

by the pipe system, on the unit!

At least one safety valve must be used 

having

 the appropriate diameter and opening pressure, in the 

system.  According to the storage capacity, the minimum safety valve diameter to be used should be 

¾” for 

800

 liters and below, 1" for 

800

-3000 liters and 1 ¼” (or 2 pcs 1”) for over 

3000

 liters. The 

opening pressure of the safety valve must not exceed 90% of the product operating pressure.

Содержание TDB Series

Страница 1: ...www tanpera com STORAGE WATER HEATER TSB and TDB Series DOMESTIC HOT WATER STORAGE TANK PRO Series INSTALLATION OPERATION AND MAINTENANCE MANUEL...

Страница 2: ...e of printing However because of rapid developments in this field we cannot be held liable for changes in specifications affecting the contents of this publication COPYRIGHT Copyright Tanpera A All ri...

Страница 3: ...er heater 5 2 PRO series domestic hot water storage tank 6 INSTALLATION 6 1 Siting 6 2 Space requirements for the installation location 6 3 Transport lifting storage 6 4 Installing the pipe connection...

Страница 4: ...s and regulations are strictly kept concerning human environment protection YELLOW TRIANGLE Refer to applicable SAFETY ALERT notices within the manuel All SAFETY ALERT notices are applicable to person...

Страница 5: ...ified Type key Type code TSB Single pipe coil storage water heater TDB Double pipe coil storage water heater PRO Hot water storage tank Total storage capacity liters Nominal operating pressure bar TSB...

Страница 6: ...be put into operation before all indistinctnesses have been solved To avoid injuries and damages follow the instructions and local applicable safety regulations Also take the necessary protective meas...

Страница 7: ...th water or water mixture which is not in operation is exposed to temperatures below zero the tank can be damaged The water heater coils are only suitable for hot water or water glycol mixtures in the...

Страница 8: ...the hot water circulated in the coil The domestic hot water supply values given in the catalog are valid if the heating water inlet temperature and the flow rate corresponding to the capacity specifie...

Страница 9: ...information 6 Hot water exit Heating inlet Hot water return Heating exit Heating inlet Heating exit Capacity 100 5000 liters Designated use Hot water not exceeding 90 C Operation pressure 10 bar Mount...

Страница 10: ...drainage system floor drain sump pit and pump etc capable of discharging water should be provided on the floor TANPERA shall not be liable for water leak damages that may be caused by the product or t...

Страница 11: ...nges in technical information 8 To lift the unit itself first remove the thermoplastic cap on top and expose the transport eyebolts Particularly for the tanks with steel sheet sleeve care must be take...

Страница 12: ...with original packaging in a closed place which is absolutely free of external weather conditions Rising of the unit The pallet should be removed before mounting To remove the pallet lay down the uni...

Страница 13: ...technician We reserve the right to make changes in technical information 10 Before filling the tank with water unused connection ports should be blocked with a blind plug Electrical control panel must...

Страница 14: ...k is completely filled with water check all connections and piping for leaks This control can be made by visual inspection or by monitoring the pressure drop from the manometer in the installation Com...

Страница 15: ...perform cleaning and periodic maintenance of your product During cleaning and maintenance tools and chemicals that may cause physical and chemical damage to the enamel should not be used Maintenance...

Страница 16: ...arranty period are excluded from the warranty if it is detected that the magnesium anode is fully depleted Install the anode in place and tighten it Open the cold water valve and continue to use the p...

Страница 17: ...es Clean the strainer filter at the cold water inlet Turbid water flowing from taps Anode is depleted or not functioning Water leakage from the unit Flange or anode seal defective Safety valve opening...

Страница 18: ...e anode Replace if finished Call TANPERA service if the problem is not resolved Tank dirty Safety valve opening Unable to compensate water expansion Safety valve opening pressure is low Pressure incre...

Страница 19: ...at hasn t been authorised by TANPERA c Products that commissioning is required but are not commissioned by our After Sales Services Department or by a service organization authorized by us d Defects r...

Страница 20: ...S WITH INDIRECT PIPE COIL ELECTRIC STORAGE WATER HEATERS DOMESTIC HOT WATER STORAGE TANKS PACKAGE TYPE DOMESTIC HOT WATER SYSTEMS BUFFER TANKS EXPANSION TANKS DEAERATORS DIRT SEPERATORS HYDROLIC SEPER...

Отзывы: