6. Commissioning
6.1 Construction
•
Ensure that there are no foreign bodies inside the device, and that all the components are
securely in place.
•
Manually check that the fan does not come into contact with the sides.
•
Make sure that mounting bolts or duct do not interfere inspection panels.
•
Make sure that all service doors and panels are closed and fastened.
•
Make sure that all connections are made correctly.
•
Check that the inspection flap is closed.
•
Ensure that ALL connections are properly made.
6.2 Electrical connection
•
Fans
CAUTION!
All installation work must only be carried out by qualified and authorised personnel
using suitable equipment.
The client and/or the installer of the electric system is responible for choosing
the equipment and cables used for connecting the fan electrically, based on
the dimensions of the motor installed and the characteristics of the main
power supply.
Depending on the level of automation offers the following options:
•
Without management – all consumers and equipment (sensors, pressure switches, electric
actuators, etc.) are displayed on the terminals, ordered in the electrical board. – fig4
Содержание EVB - HiE
Страница 1: ...Rev 2013 08 25 01 Installation and service manual of high efficient heat recovery units EVB HiE ...
Страница 2: ...Rev 2013 08 25 01 1 ...
Страница 19: ...Rev 2013 08 25 01 18 ...
Страница 20: ...Rev 2013 08 25 01 19 ...
Страница 23: ...Rev 2013 08 25 01 22 9 2 Identification plate ...
Страница 26: ...Rev 2013 07 25 01 25 ...
Страница 27: ...Rev 2013 07 25 01 26 ...
Страница 28: ...Rev 2013 07 25 01 27 ...