2.1a) Face of Wall Mount:

  Hold the unit against the opening and determine the future fit.  It is important to 

ensure that there is an even plane on which to mount the Habitat Screen.  Face of Wall mounted Habitat Screens 

come with 7/8” build up for the guide rails and panel box top to allow for bottom profile clearance. Various 

additional extruded build-up materials can be used to achieve such an even surface (below).  This additional 
build-up may be purchased from Talius.   
 

 

 

Содержание Habitat Screen

Страница 1: ...hrough a small fraction of this booklet as it covers all types of Habitat Screen installations At the beginning of each section the booklet will point out if the section can be skipped Habitat Screens...

Страница 2: ...While we do not supply common tools and hardware contact us to purchase the specialized tools like motor tester cables Please note Talius does not supply the fasteners for installation We believe this...

Страница 3: ...Talius Habitat ScreenTM Installation Guide Version 2018 1 3 TALIUS PARTS OVERVIEW...

Страница 4: ...necessarily aligned perfectly with the panel box so it s best to level the unit based upon the shaft 1 2 Guide Rails Both guide rails must be mounted plumb and true with equal spacing between from top...

Страница 5: ...ant to ensure that there is an even plane on which to mount the Habitat Screen Face of Wall mounted Habitat Screens come with 7 8 build up for the guide rails and panel box top to allow for bottom pro...

Страница 6: ...ll a pilot hole of approximately 3 8 10mm in diameter through the wall being sure to follow the same pitch as observed above Have a helper safely hold a piece of wood over the location the hole will e...

Страница 7: ...he guide rail 4 1b Between Jamb Mount Applications Guide rails will not be pre drilled unless your unit has rails that will be recessed into a post and fastened through channel and you have requested...

Страница 8: ...tion and hold the unit over the opening where you wish it to be located Install the top screw in one of the guide rails Using a 4 level and ensuring the bubble is perfectly centered between the lines...

Страница 9: ...plate to be placed underneath the universal joint to provide a stronger mounting base This is a common point of failure if a secure fastening is not accomplished in the initial install If the operato...

Страница 10: ...see a simple design in the motor configuration but this is wrong The description supplied with this job does not contain enough information to explain the intricacies of a tubular motor and it cannot...

Страница 11: ...nel power must be disconnected to additional units so that only the unit being adjusted has power After isolating a single unit preform the limit adjustment steps below and repeat for each unit Step O...

Страница 12: ...buttons on the head of the motor see diagrams below 2 Using the tester cables or switch operate the unit up until curtain stops at the temporary UP limit set by Talius 3 Unlock the UP limit switch on...

Страница 13: ...h has cut off power and will restore it automatically in 10 to 45 minutes depending on the surrounding temperature Motors are designed to run for short intervals only During limit switch adjustments t...

Страница 14: ...wall Secure each end plate with at least one 2 3 50 76mm long screw dependent upon what is suitable for the mounting surface For units in high wind installations use two fasteners per end plate as sho...

Страница 15: ...ions install a bottom stop into each guide rail 9 3 Caulking Caulking around the top of the panel box and guild rails will help to prevent water from penetrating behind the Habitat Screen and to ensur...

Страница 16: ...ow sufficient room for maneuvering the bottom profile into position As such any fasteners holding the box to the wall will have to be removed I Check to see if the fabric is tracking properly by opera...

Страница 17: ...side H Check to ensure the rail spacing is correct true and plumb from top to bottom I Check to ensure the rails are not twisted from installation A straight edge or level can be placed against the f...