PRE-INSTALLATION STEPS 

(Remove Glass Enclosure Panel)

The appliance is shipped with all gas controls 

and components installed and pre-wired. 

Note: Remove the glass enclosure panel 

before installing the fireplace. 

To remove the glass enclosure panel: 

1. Remove the shipping carton, and then re-

move the shipping pad, exposing the front 

glass panel.

2. Open  the  two  latches  securing  the  glass 

panel (under the firebox floor). 

3. Remove the glass panel by tilting it outward 

at the bottom and lifting it up.

4. Set aside the glass enclosure panel in a 

safe location to protect it from inadvertent 

damage.

TYPICAL INSTALLATION  

SEqUENCE

The typical sequence of installation is outlined 

below,  with  page  number  references  to  the 

related detailed instructions.

NOTE: Each installation is unique and may 

result in variations to these steps.

Step 1.   (

Pages 8–10

Construct the appliance 

framing. 

 

Position  the  appliance  within  the 

 framing  and  secure  with  nailing 

brackets.  

 

IMPORTANT! Bend up the appropri-

ate  top  standoff  spacers  for  the 

drywall/finish material thickness to 

be used (see Figure 7). 

Bend up the 

outer pair for 1/2" ma terials and the 

inner pair for 5/8" materials. 

 

Bend up the outer pair for 1/2" ma-

terials  and  the  inner  pair  for  5/8" 

materials. 

 

Bend  out  the  appropriate  nailing 

flanges for the drywall/finish material 

to be used. 

 

Nailing flanges are provided for flush 

framing, 1/2 inch and 5/8 inch fram-

ing depths (see 

Figure 7

).

Step 2.   (

Page 11

) Route the gas supply line 

to the appliance location.

Step 3.   (

Page 11

) Install the vent system and 

exterior termination.  

Step 4.   (

Page 12

) Install field wiring.

 

 

a.  Millivolt  Appliances:  Install  the 

operating control switch (not factory 

provided).

 

b. Electronic Appliances: Field wire 

and install operating control switch.

Step 5.   (

Page 14

) [OPTIONAL]: Install 

outside supplemental combustion 

air kit.

Step 6.  (

Page 15

) Make connection to gas 

supply.

Step 7.   (

Page 16

) Verify appliance operation.

Step 8.   (

Page 17

) Install the logs, decorative 

volcanic stone, and glowing embers. 

Step 9.   (

Page 20

Install the glass enclosure 

panel.

Step 10.  (

Page 20

Adjust burner air shutter 

to ensure proper flame appearance.

Step 11.  (

Page 22

Perform spillage test. 

Step 12.  (

Page 23

Install hood. 

Step 13.  (

Page 23

Complete finished interior 

wall. 

Step 14. (

Page 24

Attach "Safety-in-

Operation" warnings.

dETAILEd INSTALLATION STEPS

Step 1. Construct Appliance 

framing

Frame the appliance as illustrated in 

Figures 

8-1 and 8-2

.

 

All framing details must allow for 

a minimum clearance to combustible framing 

members as shown in 

Table 6

,

 Page 7

.

If the appliance is to be elevated above floor 

level,  a  solid  continuous  platform  must  be 

constructed below the appliance.

Headers may be in direct contact with the appli-

ance top standoff spacers 

when they are bent 

up vertically

, maintaining the 3" clearance to 

the fireplace top, 

but must not be supported 

by them or notched to fit around them

. All 

construction  above  the  appliance  must  be 

self-supporting. 

DO  NOT  use  the  appliance 

for structural support.

Secure the fireplace to the side framing mem-

bers using the unit's nailing flanges — one top 

and bottom on each side of the fireplace front. 

See 

Figure 7

. Use 8d nails or equivalent.

       WARNING 

failure  to  position  the  parts  in 

accordance with these diagrams 

or failure to use only parts specifi-

cally approved with this appliance 

may result in property damage or 

personal injury.

       AVERTISSEMENT 

Risque  de  dommages  ou  de 

blessures  si  les  pièces  ne  sont 

pas  installées  conformément  à 

ces schémas et ou si des pièces 

autres que celles spécifiquement 

approuvées avec cet appareil sont 

utilisées.

Figure 7

Nailing flanges are

provided at all four

corners at 5/8", 1/2",

and flush settings.

Side

Framing

Fireplace

Nailing 

Flanges

~

NOTE: The nailing flanges, combustible 

members, and screw heads in areas directly 

adjacent to the nailing flanges are EXEMPT 

from the 1/2” clearance to combustible 

requirements for the firebox outer wrapper.
Combustible framing may be in direct contact 

with the nailing flanges and may be located 

closer than 1/2” from screw heads and the 

firebox wrapper in areas adjacent to the  

nailing flanges. 
Frame the opening to the exact dimensions 

specified in the framing details in this manual.

fireplace secured to framing 

by nailing flanges

(Left side front corner of fireplace shown.

Right side requirements are the same.)

SUPERIOR

®

 B-VENT GAS FIREPLACES  •  MODELS SLBV-35, SLBV-40  •  INSTALLATION INSTRUCTIONS

8

NOTE: DIAGRAMS & ILLUSTRATIONS ARE NOT TO SCALE.

Control

Compartment

Panel

Hood

Glass

Door

Header

Spacing

Top

Standoffs

Flush

Nailing

Flange

1/2”

Nailing

Flange

5/8”

Nailing

Flange

Glass Door

Spring Latch

*IMPORTANT! 

Bend up the 

Top Standoff 

Spacers before 

installation.

Use outer pair 

for 1/2" materials 

and inner pair 

for 5/8" materials.

Top 

Standoff

Spacers*

Control

Compartment

Panel

Hood

Glass

Enclosure

Spring Latch

Panel

Lower

Enclosure Panel

Flush

Nailing

Flange

1/2"

Nailing

Flange

5/8"

Nailing

Flange

Содержание SLBV-35

Страница 1: ...PEUT CAUSER DES BR LURES LAISSER REFROIDIR LA SURFACE VITR E AVANT D Y TOUCHER NE PERMETTEZ JAMAIS UN ENFANT DE TOUCHER LA SURFACE VITR E EL VIDRIO CALIENTE CAUSAR QUEMADURAS USTED DEBE NUNCA TOCAR EL...

Страница 2: ...on system No external electrical power is required to operate these appliances however 120V AC is recommended see Step 4 Install Field Wiring on Page 12 Use Only These Approved Vent Components These v...

Страница 3: ...localcodesor intheabsenceoflocalcodes with the USA National Electrical Code ANSI NFPA 70 latest edition or in Canada the Canadian Electrical Code CSA C22 1 latest edition Provide adequate clearances a...

Страница 4: ...Table 3 Requirements for the Commonwealth of Massachusetts Thesefireplacesareapprovedforinstallationin the US state of Massachusetts if the following additional requirements are met Install this appli...

Страница 5: ...rom furniture and draperies Figure 3 En raison des temp ratures lev es l appareil devrait tre install dans un endroit o il y a peu de circulation et loin du mobilier et des tentures Figure 3 The locat...

Страница 6: ...a chimney vent servicing a solid fuel fireplace provided the B vent cap is at least 2 ft 0 6 m away from the nearest point of the chimney opening Gas Vent Rule Gas vent caps are not permitted within 8...

Страница 7: ...appliance front face blacksheetmetal Neverallowcombustiblematerialstobepositioned in front of or overlapping the appliance face see Figure 5 also see Figure 30 on Page 23 Non combustible materials su...

Страница 8: ...raming Frame the appliance as illustrated in Figures 8 1 and 8 2 All framing details must allow for a minimum clearance to combustible framing members as shown in Table 6 Page 7 If the appliance is to...

Страница 9: ...Figure 8 1 Framing Dimensions Model No A B C SLBV 35 in 35 1 4 35 1 4 16 mm 895 895 406 SLBV 40 in 40 1 4 40 1 4 16 mm 1022 1022 406 C is the required framing depth dimension when the finish material...

Страница 10: ...VER PLATE with KNOCKOUT Right Side 16 in 406 mm Hood Left Side View 5 7 8 in 149 mm NOTE It is recommended that gas be stubbed in from LEFT side only 3 in 76 mm 9 1 2 in 241 mm GAS INLET KNOCKOUT 7 3...

Страница 11: ...ions Allappliancesarefactory equippedwithaflex ible gas line connector and 1 2 inch shutoff valve See Step 6 on Page 15 Never use galvanized or plastic pipe Gas lines must be routed constructed and ma...

Страница 12: ...through the knockout opening and into the unit junction box 5 Connect the black power supply wire to the lower outlet s red pigtail lead and the white power supply wire to the common terminal of the...

Страница 13: ...tion Instructions TRANSFORMER 3V BROWN BROWN BLACK BATTERY BACK UP BLACK SENSOR BLACK IGNITER IGNITER MODULE 3V RED PILOT IN OUT VENT LO HI TH TP TH TP IN ORANGE THTP BLACK TP GREEN TH HIGH LIMIT SWIT...

Страница 14: ...the lower control compartment opening See Figure 15 To open the outside air shutter open the bottom controlaccesspanel reachintothecontrolcom partment and pull the outside air control lever all the wa...

Страница 15: ...the gas flex line Using pipe dressing materials appropriate for the gas type securely affix the shut off valve to this determined pipe length at a convenient location outside of the appliance lower co...

Страница 16: ...appliances only Note Lighting Instructions are also found on the literature tag tied to the gas piping next to the gas valve To access the tag open the lower control compartment door by pulling the pa...

Страница 17: ...2 Separate the glowing ember material into pieces about the size of a quarter Keep the pieces fluffed up not matted Distribute the pieces over the sur face of the burner as shown in Figures 23 and 24...

Страница 18: ...le at the bottom of log 4 over the nub of log 2 as shown 4 2 SLBV Firebox Accessories Parts Cat No Model No Description H7244 SLBV 35 Log Set Assembly 88L53 FGE Bag of Glowing Embers Rockwool 80L42 FD...

Страница 19: ...ent sooting make sure logs do not cover any burner openings Step 4 Align the hole at the bottom of log 5 over the Nub of log 3 as shown 3 5 Step 2 Align hole at the bottom of left front log 2 over the...

Страница 20: ...ing on both sides is even and equal Control Compartment Panel Hood Glass Door Header Spacing Top Standoffs Flush Nailing Flange 1 2 Nailing Flange 5 8 Nailing Flange Glass Door Spring Latch Control Co...

Страница 21: ...en tally to a more open position until the proper flame appearance is achieved If flame stays lowered blue adjust the air shutter incrementally to a more closed position until the proper flame appeara...

Страница 22: ...ician inspect the fireplace and venting for these conditions and repair as needed To RESET the safety limit switch push the reset button located between the wire terminals on the back of the switch Fo...

Страница 23: ...ished wall position framework to accom modate the thickness of the finished wall Figure 30 For Cold Climate Insulation see Page 5 For Clearances see Page 7 Top of Appliance 1 in 25 mm min Figure 30 Co...

Страница 24: ...sa Nettoyez soigneusement la plaque murale de l interrupteur pour liminer la poussi re et les traces de graisse ou d huile Collez l tiquette sur la surface de la plaque de l interrupteur mural qui con...

Страница 25: ...screws b Remove the pressure regulator spring poppet diaphragm and bushing c Discard all removed components d Make sure the rubber gasket in stalled on the back of the replace ment pressure regulator...

Страница 26: ...version label provided in the conversion kit next to the rat ing plate on the appliance Step 13 Turn on gas supply and test for gas leaks refer to Page 16 Always test pressures with the valve regulato...