Installation
900697-01 01/2017
Innovative Hearth Products
DRT4000 Series Direct-Vent Gas Fireplaces
21
8.
Place the Fireplace in the Framing and Secure
NOTE:
Nailing flanges, combustible members, and screw heads in areas directly adjacent to the nailing flanges are
EXEMPT from the 1/2” clearance to combustible requirements for the firebox outer wrapper.
NOTE:
Combustible framing may be in direct contact with the nailing flanges and may be located within 1/2” of screw
heads and the firebox wrapper in areas adjacent to the nailing flanges.
Frame the opening to the exact dimensions specified in the framing details in this manual.
1.
Bend out the appropriate nailing flanges for the drywall / finish material to be used
(
Figure 11
)
. Nailing flanges
are provided for:
• flush framing,
• 1/2”, and
• 5/8” framing depths.
2.
Secure the fireplace to the side framing members using the unit’s nailing flanges—one top and bottom on each
side of the fireplace front
(
Figure 11
)
. Use 8d nails or the equivalent.
Figure 11 - Nailing Flanges
Side
framing
Unit nailing flange
(no clearance to combustible
framing is required)
VENT SYSTEM PREPARATION
9.
Select a Horizontal or Vertical Vent System
1.
With the fireplace secured in the framing, determine the vent route and identify the exterior termination location.
The following sections describe vertical (roof) and horizontal (exterior wall) vent applications. Use only approved
vent components
(
Page 8
and
Pages 46-47
)
.
NOTE:
This fireplace must be vented directly to the outside.
WARNING
The vent system may not service multiple appliances, and must never be connected to a
flue serving a separate solid fuel burning appliance.
NOTE:
The vent pipe is tested to be run inside an enclosed wall (such as a chase). There is no requirement for
inspection openings in the enclosing wall at any of the joints in the vent pipe.