12
If the country code set as Other, a Grid codes
page as shown in the right will appear.
Press
to select grid code and
press
ENTER
to
confirm.
If the country selected is not the abvementioned 5 countries, enter the next step
directly.
Step 7
After selecting the Grid Code, there will be a
“Pro-stage” type selection screen and then
corresponding sub-menu will come up. For
detailed information, please refer to
“Protection Parameter Setting” in User
Manual.
Step 8
Set the inverter time as per local time.
Incorrect time setting will affect the data
logging.
Press
to move the cursor and
Press
to set the specific time and date.
Press
ENTER
to confirm setting.
Step 9
After configuring all parameters, there will be
a “setting confirmation” screen. Check
whether all above-mentioned parameters are
correct. Confirm by
Pressing
ENTER
. Cancel
by
Pressing
ESC
and reset.
Step 10
Inverter will enter into startup process.
Observe the status of LED indicators and the
LCD main screen. If commissioning succeeds,
the “RUN” indicator will be on and “Run” will
be displayed on the “State” area.
If commissioning fails, the “FAULT” indicator will be on and “Fault” will
occur on the display.
Press
to view “current fault” information.
Remove the existing fault and then repeat the commissioning
procedures.