background image

 

12  

 

If the country code set as Other, a Grid codes 
page as shown in the right will appear. 

Press 

 

to select grid code and 

press

 

ENTER

 to 

confirm.

 

 

 

If the country selected is not the abvementioned 5 countries, enter the next step 
directly. 

Step 7

 

After selecting the Grid Code, there will be a 
“Pro-stage” type selection screen and then 
corresponding sub-menu will come up. For 
detailed information, please refer to 
“Protection Parameter Setting” in User 
Manual. 

 

Step 8

 

Set the inverter time as per local time. 
Incorrect time setting will affect the data 
logging. 

Press 

 

to move the cursor and 

Press 

 

to set the specific time and date. 

Press 

ENTER 

to confirm setting. 

 

Step 9

 

After configuring all parameters, there will be 
a “setting confirmation” screen. Check 
whether all above-mentioned parameters are 
correct. Confirm by 

Pressing 

ENTER

. Cancel 

by 

Pressing 

ESC

 and reset. 

 

Step 10

Inverter will enter into startup process. 

Observe the status of LED indicators and the 
LCD main screen. If commissioning succeeds, 
the “RUN” indicator will be on and “Run” will 
be displayed on the “State” area. 

 

 

If commissioning fails, the “FAULT” indicator will be on and “Fault” will 
occur on the display. 

Press 

 to view “current fault” information. 

Remove the existing fault and then repeat the commissioning 
procedures. 

 

Содержание SG36KRL-M

Страница 1: ...uctions of the user manual and other related regulations before installing the equipment Any violation could result in personal death or injury or device damage 1 Unpacking and Inspection Step 1 Remov...

Страница 2: ...nclude quality certificate packing list product test report and quick user manual D Fastener set Six units It is used for fastening backplate onto metal frame E Fix screws 2 M4 16 screws for fix the i...

Страница 3: ...horizontal position Step 2 Mark the positions to drill holes by using the backplate as the template Step 3 Drill 6 holes at the marks you have made If the shape of the metal frame doesn t fit the hole...

Страница 4: ...n the back of the inverter fit perfectly together with the backplate Step 6 After fit the inverter to the backplate fasten the inverter to the backplate with two M4 16 screws Item Description Remark A...

Страница 5: ...er are not live before you start the electrical work Do not turn on the AC side or DC side circuit breaker until all inverter electrical connections have completed 3 1 Open the Connection Cabinet Loos...

Страница 6: ...cables Range 16 50mm2 DC Cables Cross sectional area Cable External diameter Max withstand voltage Max input current for each PV string 4 6mm2 12AWG 10AWG 6 9mm 1100V 12A Second PE Cable The cross se...

Страница 7: ...the correct polarity and that the open circuit voltage does not exceed the inverter input limit 1100V even under the lowest operating temperature Check the positive and negative polarity of the PV ce...

Страница 8: ...There is a second PE terminal on one side of the inverter and it should be grounded Fig 3 1 Second PE terminal The ground connection of this second PE terminal cannot replace the connection of the PE...

Страница 9: ...re provided on the configuration circuit board of the junction box A 120 terminating resistor can be connected between the A and B communication cable through the dip switch 3 7 Completing Installatio...

Страница 10: ...ter it is referred to as Press Press for more than two seconds Return to the previous menu or cancel the command Hereinafter it is referred to as Press ESC Press for less than 2 seconds Move left or r...

Страница 11: ...where LV signifying low voltage grid MV signifying medium voltage grid Press to select grid code and press ENTER to confirm If the country code set as TK a Grid codes page as shown in the right will a...

Страница 12: ...the data logging Press to move the cursor and Press to set the specific time and date Press ENTER to confirm setting Step 9 After configuring all parameters there will be a setting confirmation scree...

Отзывы: