SG100KU
Installation Manual
44
7.6
AC Grid Connections
To reduce the risk of fire, connect only to a circuit provided with 340A maximum
branch circuits over current protection.
When connect external AC cables to the SG100KU, positive phasing sequence must
be maintained throughout the installation process.
The connection terminals are located in the lower right corner of cabinet. Connection
process as follows:
1. Ensure that the AC grid cables with no electricity.
2. Route the Line Grid L1, L2, L3 and Neutral cables through the cable entry holes
to the AC terminals, see Fig 7-6.
3. Connect the cables to terminals marked L1, L2, L3 and N respectively, refer to
Fig 7-1.
4. Secure the AC Line cables to the terminal with screws.
Fig 7-6 AC Output Cable Routing
Содержание SG100KU
Страница 1: ...SG100KU PV Grid Connected Inverter Installation Manual SG100KU IEN Ver13 201308 Version 1 3...
Страница 2: ......
Страница 21: ...11 3 Introduction About This Chapter This chapter provides basic information about SG100KU...
Страница 70: ......