SG100KU
Installation Manual
22
4.3.2
Clarence Space
Maintain a minimum of 24inch (600 mm) clearance in back, 48inch (1200mm) in front
and 24inch (600mm) on top of the SG100KU for proper ventilation and installation
operation.
The space from the top of the enclosure to the installation site ceiling must be left
enough for ventilation and maintenance; otherwise maintenance personnel cannot
open the top panel.
Fig 4-2 Clearance Space around the SG100KU
4.3.3
Cable Trench
The external cables of the SG100KU route into or out of the cabinet via the base.
Cable trenches or steel supports above the floor are recommended (Refer to relevant
design guides or standards).
Well electrical connection is needed between different cable trenches and GND
terminals.
Содержание SG100KU
Страница 1: ...SG100KU PV Grid Connected Inverter Installation Manual SG100KU IEN Ver13 201308 Version 1 3...
Страница 2: ......
Страница 21: ...11 3 Introduction About This Chapter This chapter provides basic information about SG100KU...
Страница 70: ......