Installation
Boiler installation
Boiler installation
The boiler should be positioned in a
frost-proof boiler room. If the boiler
room is on the roof, the boiler itself may
never be the highest point of the instal-
lation.
When positioning the boiler, please
note the recommended minimum clea-
rance in the picture. When the boiler is
positioned with less free space, mainte-
nance activities will be more difficult.
Once the boiler is in the correct posi-
tion, the wooden blocks (1) should be
removed and the adjustable feet (2)
(with vibration absorption dampers)
should be adjusted to the right height.
Water and gas connections should be
done after mounting the feet, as they
effect the exact height of all connecti-
ons.
17
800
1000
The R3407- R3410 are not supplied on
wooden blocks, but on wheels. After
positioning the boiler, the adjustable
feet have to be set to the correct height.
The wheels have to be removed. The
connections to the boiler have to be
made after the feet have been ad-
justed, as the adjustment will effect the
exact height of all connections.