background image

8.1.1 - Adjusting the Tornado 600MD to fertilize  2 rows

Example:

The goal is to distribute 50 grams of granular fertilizer per coffee tree:
- The coffee was planted with a spacing of 4 meters  between rows and 1.5 

meters between plants;

- If the tractor works at 6km/h = 6000 meters in 60 minutes = 100 meters per 

minute;

- After every 100 meters traveled, 66 plants will be fertilized on either side, 

or be it, 132 plants total;

- We want to place 50 grams per plant, thus, in 1 minute the result should be:

With  the  conductor  device  for  row  distribution  already  attached  on  the 

Tornado 600MD, ajust the lever stop to a position which will correspond to 6.6 
kg/min. Next, verify this rate following these procedures:

- Operate the implement with atleast  30 kgs of fertilizer in the reservoir; 
- Using sacks, collect the product ejected in 1 minute, on both exits;
- Use this opportunity to check if both sides are ejecting the same quantities; 
- Weigh the total amount of product collected. It should weigh  6.6 kg.
Should the product quantity collected be different from the 6.6 kg, adjust the 

lever stop for more or less according to your situation, and test again. 

8.2 - Larger Agitator  (Christmas Tree)

The  larger  agitator  accessory  is  used  solely  on  powdered  products. 

Example: 

 dry limestone, organic fertilizers and humid urea. 

The function of this device is to maintain the product in the reservoir loose, 

so that the flow rates remain constant and uniform during the job. 

The components used on the agitator,  are mounted according to Figure 17.

132 plants

min.

50 grams

plant

x

=

=

6,600 g

6.6 kg/min

27

Содержание TORNADO 600MD

Страница 1: ...DELIVERY DATE IMPORTANT Warranty issues will only be address if this certificate is properly filled out at the time of delivery by technician This certificate must be presented with every warranty cl...

Страница 2: ......

Страница 3: ...NAME PHONE No OPERATOR S NAME S ADDRESS TECHNICIAN DELIVERY AGENT INVOICE No DELIVERY DATE We declare that the implement referenced in this document is being delivered under normal conditions of use a...

Страница 4: ......

Страница 5: ...that the first purchaser of the equipment is the DEALERSHIP and the second ownership will be here established as the CLIENT 3 The following conditions are basic and will be that the dealership will s...

Страница 6: ...elp by Stara personnel all these are the responsibility of the purchaser Also not inclusive are tires inner tubes electrical and electronic equipment batteries engine starter motor alternator fuel inj...

Страница 7: ...ner will not furnish solicited documentation F the hydraulic system is contaminated by impurities of unauthorized or non recommended fluids G the equipment is found to have damaged scraped illegible o...

Страница 8: ...ompromise the operation and the maintenance of the equipment PROJECT MODIFICATIONS Stara S A reserves the right to introduce project modifications of its products for the end of its improvements or re...

Страница 9: ...ements Industry AV STARA 519 N o Me Toque RS Brazil CEP 99470 000 Phone Fax 55 54 3332 2800 e mail stara stara com br Home page Jan 2011 Rev 03 www stara com br INSTRUCTION AND PARTS MANUAL Constant E...

Страница 10: ......

Страница 11: ...TABLE IV Ammonia Sulfate1090kg m 19 3 7 5 TABLE V Triple Superphosphate 00 42 00 1100kg m 19 3 7 6 TABLE VI Urea 45 00 00 765kg m 20 3 7 7 TABLE VII Pre germinated Rice 3 days IRGA 409 660kg m 20 3 7...

Страница 12: ...ses 30 10 3 3 Special Precautions 30 10 3 4 Storage 30 11 31 11 1 31 11 2 32 11 3 35 11 4 36 11 5 37 11 6 38 PARTS CATALOG TORNADO 600 MD MAJOR ASSEMBLY TORNADO 600 MD SUB ASSEMBLIES FASTENER PKG ASSY...

Страница 13: ...ed by the PTO Using certain accessories it is possible to row spread and even apply powdered products To use the equipment properly it is important that this instruction manual is read attentively and...

Страница 14: ...7...

Страница 15: ...mental in the traceability of the machine during its life cycle The ID plate is placed on the chassis of the implement 1 MAIN COMPONENTS MOD PESO kg N S RIE FAB M S ANO STARA S A IND DE IMPLEMENTOS AG...

Страница 16: ...ng pins on the 3 point hitches b Confirm the drive shaft length before hooking it up see item Mounting the drive shaft page 11 c Only hookup the PTO when the tractor is turned off d Do not stand near...

Страница 17: ...m the chassis and will be mounted in the field The reservoir is mounted to the chassis using 3 reinforced plates which can be easily removed for cleaning To proceed with the assembly mount the 3 plate...

Страница 18: ...these steps 1st Dis arm the tractor traction bar and move it to the side or remove it completely leaving room for the drive shaft 2nd Hook up the implement onto to the 3 points of the tractor hydraul...

Страница 19: ...Cat I 22 Cat II 28 Figure 05 Figure 07 Figure 08 Figure 06 75 cm max 5 cm 3 12...

Страница 20: ...e same length Figure 09 The two tubes male and female should have the minimum gap of 25mm on either side Figure 09 Avoid over cutting the tubes thus maintaining an area of engagement between the male...

Страница 21: ...1 Figure 11 Lever Stop Scale Figure 11 With the stop placed on 0 zero the slide gate should be totally closed and in 11 eleven totally open If this is not happening reposition the rod which is connect...

Страница 22: ...the adjustment rod onto the feeder plate and on the corresponding hole position the adjustment screw onto the arch Example The adjustment screw of the racquet is on the arch s 4th position the lockin...

Страница 23: ...be done with steaks to assist in guiding the operator and thus guaranteeing an uniform application OVERLAPPING ZONE USABLE WIDTH Figure 14 6 3 3 Vane Adjustment On the distribution disc there are 4 mo...

Страница 24: ...f the working area the Tornado 600MD has an adjustment resource which goes as follows 1st Turn the adjustment screw of the flow positioning disc to a side orientation either right or left side dependi...

Страница 25: ...ng speed 11 km h Working width 12m Product placement 9 hole PTO rpms 540 rpm Vane placement 3rd hole Scale opening 2 5 Placing the lever stop on the 2 5 opening position as suggested on table VI We pl...

Страница 26: ...If the cross distribution profile is not symmetrical or uniform in relationship to the tractor s travel make an adjustment to the product placement review item 6 3 2 3 7 1 TABLE I Potassium Chloride 0...

Страница 27: ...557 487 487 433 433 390 390 354 354 325 325 520 516 455 451 405 401 364 361 331 328 304 301 545 580 477 508 424 508 381 406 347 369 318 339 458 442 400 387 356 344 320 310 291 281 267 258 415 396 363...

Страница 28: ...tor Speeds Km h Job Width m Vane Positiion Place Point 6 47 100 142 201 261 281 334 386 438 246 268 295 327 368 421 491 544 530 576 623 670 716 763 810 857 694 734 607 642 540 571 486 514 442 467 405...

Страница 29: ...6 16 16 12 12 12 12 12 12 20 6 6 6 6 8 8 8 8 8 8 9 9 9 9 3 7 7 7 7 7 7 8 9 10 11 12 2 5 1 5 1 3 2 3 5 4 4 5 5 5 5 6 5 7 7 5 8 8 5 9 9 5 10 6 Scale Open Tractor Speeds Km h Job Width m Vane Position Pl...

Страница 30: ...93 131 114 5 101 5 91 5 83 76 5 101 5 89 79 71 64 5 59 71 4 62 5 55 5 50 45 5 42 56 49 44 39 36 33 49 43 38 34 5 31 29 42 37 32 29 5 27 24 5 9 9 9 9 9 9 8 8 8 7 7 7 7 2 6 6 6 6 6 6 6 7 8 9 10 11 12 1...

Страница 31: ...45 41 37 34 29 25 23 20 18 17 4 4 4 4 1 10 10 10 10 12 12 12 12 12 7 8 9 10 11 12 0 5 1 1 5 2 3 3 3 3 3 3 3 5 4 4 5 2 5 3 7 11 XI Barley BR 2 710kg m TABLE Scale Open Tractor Speeds Km h Job Width m V...

Страница 32: ...10 10 10 9 9 9 1 10 5 10 5 10 5 11 11 11 7 8 9 10 11 12 0 25 0 5 0 75 1 1 50 1 25 3 7 13 XIII Wheat CEP 27 820kg m TABLE Scale Open Tractor Speed Km h Job Width m Vane Position Place Point 6 19 30 77...

Страница 33: ...l with distance adjustments which vary from 2 to 8 meter between each other For the distribution to be equal on both sides it is necessary to adjust the product placement point see item 6 3 2 When row...

Страница 34: ...ese procedures Operate the implement with atleast 30 kgs of fertilizer in the reservoir Using sacks collect the product ejected in 1 minute on both exits Use this opportunity to check if both sides ar...

Страница 35: ...8 2 1 Main Components 1 2 3 4 5 Figure 17 1 Mixer Shaft 4 Cotter Pin 2 Mixer Guide 5 Pin 3 Mixer Blade 28...

Страница 36: ...s Chinese Hat This accessory serves as a means to avoid the direct exposure of the seeds to friction mainly for pre germinated rice using the smaller agitator inside the reservoir Figure 18 Figure 18...

Страница 37: ...uct Foreign objects inside the reservoir impeding the product output There is product built up at the product exit due to excisse humidity Adjust the flow rate see item 6 3 1 page 12 Remove the object...

Страница 38: ...ment The transmission box oil should be changed after the first 30 working hours thereafter at every 1000 hours being that the reservoir holds 0 4 liters With the Tornado 600MD leveled the oil level s...

Страница 39: ...unctionality and to avoid having to administer unnecessary maintenance procedures With this in mind it is important to a Remove all product residue which might remain inside the reservoir b Wash down...

Страница 40: ...33...

Отзывы: