ASSEMBLY cont’d
STEP 6
:
(Figure 4) Back fill around the perimeter of the Pit
Frame Assembly with 3000PSI concrete. Trowel the concrete
level with the scale frame and existing floor. Trowel the base of
the pit level with the base of the frame with a gradient toward the
centered drain, if used. Conduit and cable should be left free so
cable can be easily connected to the Platform Assembly.
STEP 7
:
(Figure 5) When the
concrete has set, remove and
discard the installation tabs and
screws. Install the four ¼” long
flat head screws into holes left by
plate removal.
Figure 4: Concrete Fill and
Installation Tabs
Figure 5: Hardware Placement
Figure 6: Cable Connection
Inside Frame
STEP 8
: Remove
the
Platform
Assembly from the Base Assembly
using a 5/32” hex wrench to remove
the four (4) mounting screws and set
aside.
STEP 9
: (Figure 6) Place the Platform Assembly
into the Pit Frame Assembly. The cable connection
will plug into the connector on the platform base.
Ensure extra cable does not interfere with platform
top.
Platform Deck Mounting
Screws (4)
Platform Deck
Platform Base
Pit Frame
Side Clearance
Adjustment Bolts (8)