902-289 6’ Spiral Slide
Page
7
Rev. 07/22/03
SportsPlay Equipment, Inc., 5642 Natural Bridge, St. Louis, MO 63120 (314) 389-4140
Blocks stabilize the posts while table stabilizes the deck.
The second method is to pre-install the (4) deck clamps so that there is 42
¼” between the holes in the deck clamps. Use a level and a marker to make
sure the clamps are level to each other. Then place deck onto clamps and
bolt. This method works but is less stable than the first method. The deck
and posts will stabilize more as you add components
Pre-install deck clamps and level.
Use ¼” Allen wrench on 3/8” by 1 ¼” button head bolt, with “T” nut. “T” nut
is on deck side of clamp so as to make tightening easier. When all (4)
clamps have been installed, posts and deck level, install roll pins.