__6) 

Install Stepping Stone Plastic Parts:

 After the cement has 

dried you can install the Stepping Stone Plastic parts. You will need 
the 5/16” x 1” bolts (3), 3/8” Flat Washers (4).  Place one 5/16” 
Flat Washer on to one of the 5/16” x 1” Button Head Bolts.  Insert 
this through the Plastic Stepping Stone (2) and into the Leg (1) on 
the bottom side of the Leg. Repeat this until the Stepping Stones 
are installed.  (See Detail A) 

__7) 

Once the concrete has set

, back fill dirt over the footing 

holes; inspect the area and components for tools, hazardous debris 
and sharp edges.  Verify all components are installed and all 
hardware is tight and then install the safety surfacing. 

__8)  

Inspect the components:

 for sharp edges and if necessary 

file them down and apply touch up paint. 

 

 