Initial inspection and preliminary checkout procedures are
recommended. For safe operation, please follow the
procedures described in Chapter 3, Operating Instructions.
2.1 Initial Inspection
Inspect the packaging exterior for evidence of damage
due to improper handling in transit. Notify the carrier and
Spellman High Voltage immediately if damage is evident.
Do not destroy or remove any of the packing material
used in a damaged shipment.
After unpacking inspect the power supply for any visible
signs of damage.
2.2 Mechanical Installation
V6 units can be mounted in any position using the tapped
holes in the base plate. 8-32 screws are required for
mounting. Please see the V6 series data sheet for a more
detailed dimensional drawing.
2.3 Temperature Consideration
It is the user’s responsibility to maintain the case
temperature below 50°C. Damage to the power supply
due to inadequate cooling is considered misuse and
repairs will not be covered under warranty
.