6               Installation Manual 

Vortceptor

D. BED AND

BACKFILL

Proper backfill selection and compaction is required for 
a proper installation. The allowed backfills are shown 
in Table D-1 along with the degree of compaction 
required.

TABLE D-1

BED AND BACKFILL COMPACTION

Soil type-pipe bedding 
material (Unified Soil 
Classification System - 
see Table D-2)

Minimum Degree of 
Compaction Required*

Fine - grained soils 
(Liquid Limit < 50) with 
medium to no plasticity 
with less than 25% coarse 
grained particles.
CL, ML, ML - CL

High

Fine grained soils (Liquid 
Limit < 50) with medium 
to no plasticity with more 
than 25% coarse grained 
particles.
CL, ML, ML - CL

Moderate

Coarse grained soils 
containing more than 12% 
fines.
GM, GC, SM, SC

Moderate

Coarse grained soils with 
less than 12% fines.
GW, GP, SW, SP

Slight

Coarse grained soils with 
less than 12% fines.
GW, GP, SW, SP

Dumped

* Degree of compaction:

• 

Dumped - No compaction effort.

• 

Slight - Some compactive effort. In-place density 
<85% standard compaction. Or < 40% modified 
compaction.

• 

Moderate - Intermediate level of compactive 
effort, In-place density >/=85% and < 95% standard 
compaction, or >/=40% and <70% modified 
compaction.

• 

High - Considerable compactive effort. In-place 
density >/= 95% standard compaction, or >/= 70% 
modified compaction

• 

The difference in the “dumped” and “slight” degree 
of compaction values are significant and are based 
on the method of construction, not the measured 
densities.

• 

“Dumped” means that there is absolutely no 
compaction of the embedment soil.“Slight” means 
there was something done that increased the soil 
density, even if minor, such as water settling, jet-
ting, flooding, equipment travel, and in some cases, 
foot traffic.

• 

For stable soils (cohesion ≥ 36 kpa and / or a 
bearing capacity ≥ 170 kpa a minimum 300mm of 
backfill must be placed around the wetwell.

• 

For unstable soils (cohesion ≤ 36kpa and ultimate 
bearing capacity ≤ 170 kpa).

• 

Wetwells 1200mm diameter or smaller require 
a minimum 600mm of backfill around the entire 
circumference of the wetwell.

• 

Wetwells larger than 1200mm diameter require 
a minimum backfill of ½ the wetwell diameter 
around the entire circumference of the wetwell.

• 

If muck, bog or peat are present, consult with a 
Geotechnical Engineer for backfill and excavation 
requirements.

• 

For permafrost conditions, consult with a Geotech-
nical Engineer for backfill and excavation require-
ments.

Keep backfill dry and free of ice in freezing conditions. 
Ensure that no foreign objects such as large stones, 
concrete clumps, tree roots/limbs, or debris is in the 
backfill surrounding the wetwell.

Prevent large surges of backfill from displacing the 
wetwell.

TABLE D-2

LETTER AND 
DEFINITION

SECOND LETTER  
AND DEFINITION

G                     Gravel
S                     Sand
M                    Silt
C                    Clay
O                    Organic

P       Poorly Graded
         (uniform particle sizes)
W      Well Graded
         (diversified particle sizes)
H       High Plasticity
L       Low Plasticity

Содержание Vortceptor

Страница 1: ...SPEL Vortceptor spel com au Installation Manual ...

Страница 2: ...y of all the individuals involved in the installation To prevent wetwell damage and or failure which could lead to product loss and environmental contamination To validate the wetwell warranty GENERAL INFORMATION WARNING Wetwells are a confined space per OHS guidelines Follow proper confined space safety procedures SPEL fibreglass wetwells are designed for installation with concrete top pad and bo...

Страница 3: ...tank YES NO Install a 150mm thick compacted base This can be either a concrete blinding or compacted crushed rock layer YES NO Lower the Vortceptor into the excavation ensure no rocks or sharp objects fall into the hole and damage the tank YES NO Level and adjust the Vortceptor to suit the main drain pipework and the Diversion Chamber inlet void The invert levels of the inlet and outlet pipework i...

Страница 4: ...DS bit to drill the bolt holes YES NO Use M8 x 100mm Galvanised screw bolts to fix the Vortceptor to the Diversion Chamber YES NO Associated Drainage Finishing Works Install upstream and downstream drainage pipework YES NO Connect the pipework by others to the Diversion Chamber concrete bandage the inlet and outlet pipes to the Diversion Chamber YES NO Internally render the inlet and outlet pipewo...

Страница 5: ...ntal contamination A HANDLING PREPARATION WARNING Do not stand on or under wetwell while it is being lifted This could result in personal injury or death Do not drop or impact the wetwell Wetwells should be stored horizontally and chocked using only appropriate materials such as sandbags tires or other soft or pliable materials Upon wetwell delivery and when lifting wetwell visually inspect entire...

Страница 6: ...are significant and are based on the method of construction not the measured densities Dumped means that there is absolutely no compaction of the embedment soil Slight means there was something done that increased the soil density even if minor such as water settling jet ting flooding equipment travel and in some cases foot traffic For stable soils cohesion 36 kpa and or a bearing capacity 170 kpa...

Страница 7: ...as an underground fibreglass tank the backfill around the wetwell must also meet the tank backfill requirements so as to not compromise the tank installation Tank backfill requirements are more restricted and strict conformance to the tank backfill requirments in MAN 600 must be met for both the wetwell and tank F PIPING PENETRATIONS FITTINGS CAUTION Always wear safety glasses and protective cloth...

Страница 8: ...ned to be self supporting after cured The pad shall be specified by the Certified Engineer FIBREGLASS FLAT TOPS WITHOUT TRAFFIC LOAD See Figure H 1 The pad must be larger than the wetwell a minimum of 300mm in all directions Maximum 200mm concrete pad thickness FIBREGLASS FLAT TOPS WITH TRAFFIC LOAD See Figure H 2 The pad must be larger than the wetwell a minimum of 600mm in all directions The Cer...

Страница 9: ...spel com au 9 ...

Страница 10: ...10 Installation Manual Vortceptor ...

Страница 11: ...in minimum water level Add a minimum of 300mm of well placed backfill material MUST be crushed gravel to the hole and level the bed to assure uniform bottom support for the tank Position the tank in the hole Partially ballast tank using water until it settles firmly on the prepared bed Ballast level in a tank must never exceed water level in hole during installation Use only enough ballast to sink...

Страница 12: ...ab Thickness mm Required Ballast Extension Around Wetwell mm Ballast Height mm 1200 1 1800mm Dia N12 400 200 300 400 1520 1 1920mm Dia N12 500 200 350 500 1850 1 2250mm Dia N12 1 2650mm Dia N12 550 200 400 600 2200 1 2600mm Dia N12 1 3000mm Dia FN12 700 200 500 700 2470 1 2900mm Dia N16 1 3300mm Dia N16 800 250 500 800 3000 1 3400mm Dia N16 1 3800mm Dia N16 900 300 700 1000 3500 1 3900mm Dia N20 1...

Страница 13: ...spel com au 13 ...

Страница 14: ...A OFFICE 9 Hampden Road Mount Barker SA 5251 P 1300 773 500 E sales spel com au WA OFFICE 2 Modal Crescent Canning Vale WA 6155 P 61 8 9350 1000 P 1800 335 550 E sales spel com au NZ OFFICE AUCKLAND 100 Montgomerie Road Airport Oaks P 64 9 276 9045 E sales spel com au NZ OFFICE WANGANUI 43 Heads Road Wanganu New Zealand P 64 6 349 0088 E sales spel com au NZ OFFICE WELLINGTON 41 Raiha St Porirua W...

Отзывы: