36
Commissioning
This chapter describes the commissioning
process.
The commissioning process is accomplished
using the storage system's internal web server.
Therefore, an Internet connection is required for
commissioning the unit.
If Internet service to the house has not been
installed, you can create a network using a wireless
router or network extender and pairing it with a
smartphone.
If a network connection has not been
established, the commissioning process cannot be
completed.
Commissioning checklist
▶
The following items should be checked before
starting the system.
Prerequisites
☐
The mounting location fulfills the
requirements listed on page 15.
☐
All DC bus bars and wires are
connected properly.
☐
All Modbus cables are connected
properly.
☐
The overcurrent protection of the
storage system is sized properly.
☐
The electrical connections fulfills all
requirements of local, regional, and
national regulations.
☐
The main distribution panel
and protected loads panel are
electrically isolated
☐
The electrical connections of
the storage system have been
performed correctly.
☐
The storage system has been
connected to the Internet.
Table 4 Commissioning prerequisites
Turn on the storage system
The main DC circuit breaker F1 and the switch S1
are located in the interior of the main cabinet.
Fig. 50 Switch and circuit breaker
(1) Switch
(2) Main circuit breaker
Attention
Damage of the storage system by high
currents!
High currents can damage components of the
storage system if the process is not followed
properly.
▶
Turn on the storage system only according to
the steps below.
1. If an emergency switch is installed, ensure
it is not activated. See page 28 for more
information.
2. Press switch S1 for at least 7 seconds and
keep it pressed for the next step.
3. Turn on main circuit breaker F1 of the main
cabinet.
4. Release switch S1.
OFF
OFF
OFF
OFF
Содержание sonnenBatterie ecoLinx 10
Страница 2: ......
Страница 4: ......
Страница 8: ......
Страница 17: ...9 Dimensions Fig 1 Storage system dimensions Key components Fig 2 ecoLinx key components...
Страница 30: ...22 page 23 page 23 page 29 page 23 Fig 22 Terminal map for ecoLinx...
Страница 53: ...45 Appendix 1 Nameplates...
Страница 54: ...46...
Страница 55: ...47...
Страница 61: ...53...
Страница 62: ......
Страница 63: ......
Страница 64: ...sonnen Inc 2048 Weems Road Suite C Tucker GA 30084 T 1 310 853 2404 E info sonnen batterie com PN 28336 Rev 003...