5. Installation
5. Installation
5.3.2 Step
Please reserve enough distance from the equipment to the ceiling/ground for
capacity expansion.
Take Scheme C as an example.
Step 1: Place Base.
(1) Remove the dust cover.
(2) Insert M8*85 Adjustment Screws (2) from the bottom of Base, to ensure that the
Base is even.
(a) Use a spirit level to measure the sides of the Base to ensure they are even.
(b) If not, please adjust the Adjustment Screws by a torque wrench being to ensure
that the Base is even.
Note!
Step 2: Locate the Base 1.57 in./40 mm away from the wall, accurately mark the
location of the Base on both sides with a pen.
Step 3: Place Battery Module on the Base.
(1) Remove the top and bottom dust covers.
(2) Place the Battery Module on the Base.
20
21
Right View
If the Base is shifted after placing a Battery Module, move it to its original location
according to the mark previously drawn.
Note!
1.57 in
40 mm
1.57 in
40 mm
Mark