5. Installation
5. Installation
5.1 Installation Environment Requirements
●
Ensure that the equipment is installed in a well ventilated environment.
●
To prevent fire due to high temperature, ensure that the ventilation vents or
heat dissipation system are not blocked when the equipment is running.
●
Do not expose the equipment to flammable or explosive gas or smoke. Do
not perform any operation on the equipment in such environments.
●
Make sure the wall is strong enough to withstand the weight of battery. In
case of wooden wall, it must bear the load of at least 551.16 lbs/250.00 kg.
●
Keep at least 1.5 in/38 mm away from the edge of concrete bricks.
●
In case of Wall Mounting, do not install on the hollow concrete block wall.
5.2 Installation Mode
There are two alternative installation modes (wall mounting and floor
mounting) and three schemes available for users. Please leave sufficient
room for adding battery modules.
5.3 Wall Mounting
5.3.1 Overview
4 kinds of stub spacing are provided in Plotting Sheet. There are three
schemes available for users:
Scheme A: In BMS + Two Bat Base S Base;
●
Scheme B: Inverter + BMS + Three Batteries + Base Support + Base
(Ignore hole locations of Base Support in Scheme A);
●
Scheme C: In BMS + Four Bat Base S Base (Ignore
hole locations of Base Support in Scheme A & B).
For example: In case of Scheme A with a stub spacing of 32 in/812.80 mm,
please fold along dashed line B-A and punch the holes (Battery: A-32*4 &
WB-32*2; Inverter: WB-32*4) (See markings in Figure 1).
Before installation, please determine the inverter's location, and punch holes
strictly in accordance with the stub spacing in the Plotting Sheet.
5.3
Floor Mounting
5.3.1 Overview
There are three schemes available for users.
5.1 Installation Environment Requirements
●
Ensure that the equipment is installed in a well ventilated environment.
●
To prevent fire due to high temperature, ensure that the ventilation vents or heat
dissipation system are not blocked when the equipment is running.
●
Do not expose the equipment to flammable or explosive gas or smoke. Do not
perform any operation on the equipment in such environment.
●
A distance of at least 11.81 in./300 mm shall be set aside from the equipment to
both left and right sides.
●
In case of Wall Mounting, make sure the wall is strong enough to withstand the
weight of battery. In case of wooden wall, it must bear the load of at least 2,204.62
lbs/1,000.00 kg.
●
In case of Wall Mounting, do not install on the hollow concrete block wall.
5.2 Installation Mode
There are two alternative installation modes and three schemes available for users.
For details, refer to the following table.
A distance set aside from the equipment to the ground may be determined
according to regulations at the place where the user is located.
BMS
Battery
Module
Base
BMS
Battery
Module
Base
Base
Support
Scheme A
1
2
1
1
2
1
1
Scheme B
1
3
1
1
3
1
1
Scheme C
1
4
1
1
4
1
1
Wall Mounting
Floor Mounting
Note: The equipment supports the following stub spacing: 20, 24, 28 and 32 in.
5. Installation
Scheme A
Distance from the equipment:
To left side:
≥
11.81 in./300 mm
To right side:
≥
11.81 in./300 mm
16
17
BMS
Battery
Battery
Base
BMS
Battery
Battery
Base
31.81 in./808 mm
2 * Wall Bracket
2 * Expansion Bolt
2 * Tapping Screw
2 * Gasket
14 * M5*10 Screws
2 * Platen (3 holes)
4 * Platen (2 holes)
BMS
Battery
Battery
Base