② We are recommending for soft ground: use anchor bolts to install the bollard per to the
below.
1. Dig a hole, size 13.77 in(L)*13.77in(W) *7.87in(H).
2SPBL1, 2SPBL2, 2SPBL3, 2SPBL4, 2SPBL5, 2SPBL6, 2SPBL7, 2SPBL8, 2SPBL9, 2SPBL10,
2SPBL12 series see picture 5
,
2SPBL11 series see picture 6.
Picture 5
Picture 6
2.
As above picture 5 and picture 6, wrap screw thread with scotch tape to prevent cement,
then put metal holder in the middle of hole, adjust the best position.
3.
Cover metal holder with cement, and preserve 1.57 inch screw pole.
Use level ruler Adjust the position of metal holder
(
2SPBL1, 2SPBL2, 2SPBL3, 2SPBL4,
2SPBL5, 2SPBL6, 2SPBL7, 2SPBL8, 2SPBL9, 2SPBL10, 2SPBL12 series see picture 7
,
2SPBL11
series see picture 8
)