6 Commissioning
Installation Manual
SPW-WebconPB-IA-en-10
29
6.4.2 Registering a Large-Scale PV Plant with Cluster Controller in
Sunny Portal
Requirements:
☐ The large-scale PV plant with Cluster Controller must be commissioned (see Section 6.1).
☐ The inverter with Piggy-Back must be in feed-in operation.
☐ The Cluster Controller must be connected to a router with Internet connection
(see Cluster Controller installation manual).
☐ Your computer must have an Internet connection.
☐ JavaScript must be activated in the Internet browser.
Procedure:
• For large-scale PV plants with Cluster Controller, register in Sunny Portal using the
Cluster Controller user interface (see Cluster Controller user manual).