Installation Requirements
SMA
Technologie AG
Page 20
SBTLHCMS-IEN080411
Installation Guide
The Sunny Boy is designed for operation on 220 - 240 V grids at a grid frequency of
50 Hz. When connecting an inverter to the public grid, follow the connection require-
ments of the local grid operator.
Limit values for AC output
Voltage range
(in the area of application of DIN VDE 0126-1-1)
198 V ... 260 V
a)
Frequency range
(in the area of application of DIN VDE 0126-1-1)
47.55 Hz ... 50.2Hz
Voltage range
(extended operating range)
180V ... 260 V
Frequency range
(extended operating range)
45.5 Hz ... 52.5Hz
a)
The Sunny Boy can temporarily feed power into the grid with a maximum output
voltage of 260 V. However, DIN VDE 0126-1-1 stipulates that the 10-minute
average must not exceed a voltage of 253 V. That means, if the grid voltage is
continuously 254 V (e.g.), the inverter disconnects itself from the grid. In this
case, contact the local grid operator for assistance.
DIN VDE 0126-1-1 only applies in Germany. See section 8.4. 3 "Country-spe-
cific Parameter Settings" (Page 43) for all other preset country values of your
inverter.
Содержание SB 4200TL HC
Страница 2: ......
Страница 6: ...Explanation of the Symbols Used SMA Technologie AG Page 6 SBTLHCMS IEN080411 Installation Guide...
Страница 10: ...Safety Instructions SMA Technologie AG Page 10 SBTLHCMS IEN080411 Installation Guide...
Страница 30: ...Installation SMA Technologie AG Page 30 SBTLHCMS IEN080411 Installation Guide...
Страница 44: ...Technical Data SMA Technologie AG Page 44 SBTLHCMS IEN080411 Installation Guide...
Страница 46: ...Inspection of the Electronic Solar Switch SMA Technologie AG Page 46 SBTLHCMS IEN080411 Installation Guide...
Страница 60: ...The Communications Interface SMA Technologie AG Page 60 SBTLHCMS IEN080411 Installation Guide...
Страница 63: ......