4. Installing the MultiHaul™ TG Units
4.10 Link Up Verification
4.10.1
Node Checks
Perform the following checks on each node:
1.
Verify that node sector 1 is pointing to the azimuth specified for the site.
2.
Verify the self-locking bands are tightened.
3.
Verify that the unit has been properly grounded.
4.
Verify that the PWR LED is green.
4.10.2
TU Checks
Perform the following checks on each TU:
1.
Point the TU towards the serving node (see
Section 4.7 - Mounting and Aligning the MultiHaul™ TG TU on a Pole
or Wall
.
2.
Verify the self-locking bands and the elevation lock bolts are tightened.
3.
Verify that the PWR LED is green.
4.
Verify that the RF LED is green, indicating correct association with the serving node (Link Up).
4.10.3
Configuring the System
The MultiHaul™ TG units can now pass management and traffic between the units over the radio link, to/from the
ethernet ports.
You can use the GUI or CLI for advanced configuration of the units, monitoring their status and troubleshooting.
If you mounted the TU using the EH-MK-SM mounting kit, verify the elevation and
azimuth lock bolts on the mounting kit are tightened.