Commissioning
7.3 Commissioning procedure
S-1FK7 DYA G2 synchronous motors with planetary gearbox
78
Operating Instructions, 05/2018, A5E44881183B AA
7.3
Commissioning procedure
Commissioning
Precondition
●
You have worked through the commissioning checklists.
●
Ensure that the converter is correctly parameterized.
●
Check whether sufficient heat is dissipated from the motor.
Note
EMERGENCY OFF
To avoid accidents, inform yourself about the EMERGENCY OFF function before you switch
on the system.
Procedure
1. Commission the motor using an appropriate commissioning tool, e.g. "STARTER".
2. Follow the steps of the commissioning tool.
3. Observe any uneven running and abnormal noise of the motor.
4. Check the function of the safety equipment.
5. Check whether the motor reaches the required parameters.
You have commissioned the motor.
❒
Switching off
●
Switch off the motor at the frequency converter.