9.1.5
General inspection
Check that the installation conditions are observed. We recommend that the following checks
are performed after approx. 16 000 operating hours or at the latest after two years:
Table 9-2
Checks that have to be performed during the general inspection
Checking
When the
motor is
running
At stand‐
still
The electrical parameters are maintained
X
The permissible bearing temperatures are not exceeded
X
The smooth running characteristics and machine running noise have not
deteriorated
X
The motor foundation has no cracks and indentations (*)
X
X
The machine is aligned within the permissible tolerance ranges
X
All the fixing bolts/screws for the mechanical and electrical connections have
been securely tightened
X
All the potential connections, grounding connections and shield supports are
correctly seated and properly bonded
X
The winding insulation resistances are sufficiently high
X
Any bearing insulation is fitted as shown on the plates and labels
X
The CABLES and insulating parts and components are in good condition
and there is no evidence of discoloring
X
(*) You can perform these checks while the motor is at standstill or, if required, while running.
NOTICE
If you detect any deviations during the inspection, you must rectify them immediately. They
may otherwise cause damage to the machine.
9.1.6
Servicing the roller bearings
When inspecting rolling-contact bearings, it is generally not necessary to dismantle the
machines. The motor only has to be dismantled if the bearings are to be replaced.
All machines marked in accordance with Directive 94/9/EC (“Explosion Protection Directive”,
until April 19, 2016, according to Directive 2014/34/EU from April 20, 2016) must be regularly
Maintenance
9.1 Inspection and maintenance
LOHER CHEMSTAR 1PS2
88
Operating Instructions 08/2016
Содержание LOHER CHEMSTAR 1PS2
Страница 2: ...04 08 2016 11 45 V3 00 ...
Страница 12: ...Introduction 1 1 About these instructions LOHER CHEMSTAR 1PS2 12 Operating Instructions 08 2016 ...
Страница 38: ...Preparations for use 4 13 Transport and storage LOHER CHEMSTAR 1PS2 38 Operating Instructions 08 2016 ...
Страница 64: ...Electrical connection 6 2 Connecting LOHER CHEMSTAR 1PS2 64 Operating Instructions 08 2016 ...
Страница 74: ...Start up 7 8 Test run LOHER CHEMSTAR 1PS2 74 Operating Instructions 08 2016 ...
Страница 84: ...Operation 8 11 faults LOHER CHEMSTAR 1PS2 84 Operating Instructions 08 2016 ...
Страница 102: ...Maintenance 9 2 Corrective Maintenance LOHER CHEMSTAR 1PS2 102 Operating Instructions 08 2016 ...
Страница 118: ...Service and Support LOHER CHEMSTAR 1PS2 118 Operating Instructions 08 2016 ...
Страница 120: ...Technical data and drawings LOHER CHEMSTAR 1PS2 120 Operating Instructions 08 2016 ...
Страница 121: ...Quality documents C C 1 EC Declaration of Conformity LOHER CHEMSTAR 1PS2 Operating Instructions 08 2016 121 ...
Страница 122: ...Quality documents C 1 EC Declaration of Conformity LOHER CHEMSTAR 1PS2 122 Operating Instructions 08 2016 ...
Страница 138: ...Quality documents C 2 IECEx certificate LOHER CHEMSTAR 1PS2 138 Operating Instructions 08 2016 ...
Страница 142: ...Index LOHER CHEMSTAR 1PS2 142 Operating Instructions 08 2016 ...
Страница 143: ...AD EC Declaration of Conformity U161 ...
Страница 144: ...Siemens AG Process Industries and Drives Postfach 48 48 90026 NÜRNBERG GERMANY www siemens com drives ...