=USNJVOTPKV=G=fkpq^iiqflk=fkpqor`qflkp=Ua^=G=oÉîáëáçå=MP
11
fåëí~ää~íáçå
• Shim plates 0.5 to 1 mm
• Cleaning agent HAKU 1025/90
• Soft, lint-free cloth
• Torx reversing ratchet / screwdriver T10/80, T20/100, T25/100, T30/115
• Water level
• Guide string
• Rod magnet with flexible shaft
• Open spanners SW 13, 16, 17, 18, 19, 24, 27, 32 , 36
• Ring spanners SW 13, 16, 17, 18, 19, 22, 24, 27
• Various screwdrivers
• Vernier caliper
• Water pump pliers
• Mirror with flexible shaft (welding mirror)
5.6
Installation and fixing material
Before starting to install the individual components, provide for the required installation
and fixing material.
6
Unloading and erecting the transport units
6.1
Packing and transport unit
Packing
The transport units can be packed as follows:
• on pallets, covered with PE protection sheeting
• in a seaworthy crate (switchgear is sealed with desiccant bags in PE protection sheet-
ing)
• other packings in special cases.
Transport unit
Transport units consist of:
• Individual panels or panel groups consisting of up to 4 individual panels
• Accessories
6.2
Checking the delivery for completeness and transport damage
Before installation, the transport units must be checked for completeness and damage.
NOTE!
The packing materials of 8DA switchgear can be disposed of as classified materials. Please observe the local
regulations for disposal and environmental protection.