5 Configuration
5.1 Procedure
Configuration is handled in steps with the aid of the „PRB-Checker“ tool and
application-specific data as described below.
1. Checking to see whether there is a need for dividing the layout into multiple DP
master segments.
Prerequisites:
-
Knowledge of the total number of vehicles in the plant
-
Knowledge of the maximum permissible typical bus cycle time for the
application
Division of the layout is always required when:
-
there are more than 125 vehicles in the plant
or
-
shorter typical bus cycle times are required
or
-
the base load of the infeed PRB is to be reduced
Result:
-
Number of DP master segments
-
Transmission
speed
used.
2. Checking to see whether there is a need to divide the number of DP master
segments specified in Step 1 into multiple PRB segments. This step must be
performed separately for each DP master segment specified in Step 1.
Prerequisites:
-
Results from Step 1
-
„PRB Checker“ configuring tool
-
Layout of the plant with dimensions
-
Number of slaves in the relevant DP master segment
-
Number of vehicles in the relevant PRB segment. Each Power Rail Segment
Controller connected to the segment also has to be treated as vehicle.
-
Length of the cable between collector and vehicle
-
Maximum length of the data in the input/output bytes to be interchanged
between stationary control system and vehicle control system.
Division is always required when it is not possible
-
to supply the entire rail length of the relevant DP master segment
or
-
to supply the maximum possible number of vehicles in the relevant DP
master segment
with a stationary PRB.