Output terminals of the QM-MA-01

manual/auto control box

Output terminals of the

JB-QBL-QM200 fire alarm controller

Terminal name (meaning)

1

Terminal 1 of the master control board

+24V(+24V power supply)

2

Input terminal

GND(between 18 and 19)of the master

control board

AGND

3

Terminal 20 on the master control

board

A/M(manual/auto signal input terminal)

4

Input terminal

GND(between 18 and 19)of the master

control board

AGND

5

Terminal 7 on the master control board

Fire alarm output terminal

6

Terminal 3 on the master control board

Release output terminal

Note in the access mode above that before the fire alarm controller is delivered, the black short wire
connected to terminal 20 on the master control board should be dismounted and terminals 2 and 4 in the
manual/auto control box may be first connected to the manual/auto control box through a conductor and
then connected to the input terminal GND (between 18 and 19) on the master control board through a
conductor.

2.

QM-AN-01 emergency start/stop control box

The access mode of the QM-AN-01 in JB-QBL-QM200 is given in the table below.

Output terminals of the QM-AN-01

emergency start/stop control box

Output terminals of the

JB-QBL-QM200 fire alarm controller

Terminal name (meaning)

1

Input terminal

GND(between 18 and 19)of the master

control board

AGND

2

Terminal 1 on the master control board

+24V(+24V power supply)

3

GND(between 18 and 19)

AGND

4

Terminal 19 on the master control

board

Input terminal of the emergency stop

signal

5

Terminal 1 on the master control board

+24V(+24V power supply)

6

Terminal 17 on the master control

board

Input terminal of the emergency start

signal

7

Terminal 7 on the master control board

Single fire alarm active output terminal

Note in the access mode above that before the fire alarm controller is delivered, the black short wire
connected to terminal 19 on the master control board should be dismounted, terminals 1 and 3 in the
emergency start/stop control box may be first connected through a conductor and then connected to the
terminal GND (between 18 and 19) on the fire alarm controller through a wire and terminals 2 and 5 in
the emergency start/stop control box may be first connected through a conductor and then to the +24V
terminal (terminal 1 of the fire alarm controller) through a wire.

2.6 Power-on test

Before its delivery, the system must be tested comprehensively.

Before the power-on test, please check again if all connecting wires (including the battery lines) have
been well connected. Then press the AC switch and the DC switch on the switching power supply
(PS-06) to power the system on.
See Chapter VI for key on/off operations and Chapter V for panel indications.
Take this User’s Manual as a reference and check if all functions of the system are normal. The
EMERGENCY START button on the display panel is a disposable and fragile plastic button and it may
be tested by having the jumper JP11 on the back of the display panel shorted to the ON position.
If it is found when the system is tested that resetting of the fire alarm controller or other abnormal
phenomena occur due to a too large load starting impulse current, the usual measure is to use a 24V
external control power supply. Another measure is to have a 10~20

Ω

/3W current-limiting resistor

connected in series in the driving circuit, or to have freewheel diodes (such as IN4001) connected
reversely and in parallel at both ends of the load, or to use a resistance-capacitance network or a TVS
transient voltage suppressor (such as P6KE33CA).

2.7 Wiring diagram

Содержание JB-QBL-QM200

Страница 1: ...1 JB QBL QM200 Fire Alarm Control Panel Agent Releasing Control Panel...

Страница 2: ...de of emergency release delay 11 3 1 4 Setup of the delay mode for the EXTERNAL MANUAL RELEASE button 11 3 1 5 Setup of the control mode of the key lock over the EMERGENCY RELEASE button on the displa...

Страница 3: ...ase refer to Chapter V Panel Display and Chapter VI Key On Off Warning It is necessary to dismount all electromagnetic valves electric detonators from the devices which are driven by them during syste...

Страница 4: ...ifications 1 AC input voltage AC 220V 20 50Hz AC input power 120W DC standby power DC24V 7 0Ah consisting of two fully sealed maintenance free DC12V 7 0Ah storage batteries connected in series 2 Outpu...

Страница 5: ...he display panel and displays the start countdown The delay manner of the manual start may also be set by the user through the jumpers on the display panel too 11 It provides an open circuit fault det...

Страница 6: ...N OFF Fig 2 1 Installation Holes of the Case The following requirements should be met during installation of the case There must be a space of at least 1m reserved in front of the case There are cable...

Страница 7: ...ecessary to have the AC supply voltage accessed with the help of a voltage stabilizer with a power of larger than 300W or else the switching power supply may be damaged The standby batteries if fully...

Страница 8: ...ate ground wires The installation and connection of the system should comply with the requirements of national standard Code for the Installation and Acceptance of the Fire Alarm System GB50166 92 Bui...

Страница 9: ...he master control board Single fire alarm active output terminal Note in the access mode above that before the fire alarm controller is delivered the black short wire connected to terminal 19 on the m...

Страница 10: ...Page 7 Fig 2 7 Wiring Diagram of the Fire Alarm Controller Active Output...

Страница 11: ...Page 8 Fig 2 8 Wiring Diagram of the Fire Alarm Controller Partial Passive Output...

Страница 12: ...nal input circuit JP16 Not detect the open fault of the Local Manual Auto signal input circuit JP17 Detect the open fault of the signal input circuit of the detector circuit 2 JP18 Not detect the open...

Страница 13: ...n fault of the stop signal input circuit Detect the open fault of the stop signal input circuit JP21 Not detect the open fault of the manual release signal input circuit Detect the open fault of the m...

Страница 14: ...he emergency release delay The factory default is OFF that is to say the electromagnetic valves will be started after the set delay time is reached All possible settings of the jumper JP5 are given in...

Страница 15: ...h means that the EMERGENCY RELEASE button is not controlled by the key lock All possible settings are given in the table below The EMERGENCY RELEASE button on the display panel is controlled by the ke...

Страница 16: ...Page 13 Fig 4 1 Terminal Positions...

Страница 17: ...ut circuit ground and the output circuit ground The 24V PGND has been connected with the output circuit ground in the control board 4 2 2 Connection modes of input terminals The local input signals in...

Страница 18: ...an open circuit fault detection function is selected the jumper JP20 on the master control board should be set to the ON position as shown in Table 3 1 2 and Fig 4 1 and the built in termination resi...

Страница 19: ...s in the control board should not be used and a 10K termination resistor should be arranged at the end of the circuit shown in connection mode B 2 A short circuit of the switch suggests a reset status...

Страница 20: ...ly The connection modes of passive output circuits are related to the actual use and will not be introduced here Connection modes of the output circuits Connecti on mode Type of load Connection mode A...

Страница 21: ...re alarm will be forbidden even if the compound fire alarm is detected by the detectors The EMERGENCY RELEASE button can still work at this time 3 Terminal 3 on the master control board It is for the...

Страница 22: ...t on whether the output circuit has a short or open circuit fault detection function When the connection mode with a short or open circuit fault detection function is selected the jumper JP6 on the ma...

Страница 23: ...T ZONE 2 RELEASE HORN STROBE FAULT MANUAL AUTO RELEASE DELAY RELEASE START RELEASE CONFIRM PANEL MUTE DISPLAY TEST ALARM BELL RESET DELAY STOP QUERY QUERY TIME KEY ON OFF Fig 5 1 Schematic Diagram of...

Страница 24: ...ator light will be lit RELEASE After the system has entered the release status and the electromagnetic valves have been started this indicator light will be lit HORN STROBE FAULT After a short or open...

Страница 25: ...M BELL After the alarm bell is started this indicator light will be lit DELAY STOP After the DELAY STOP button is pressed when the system is in the countdown for release the delay process will be stop...

Страница 26: ...ted the HORN STROBE START indicator close to this key will be lit ALARM BELLIf this key is pressed after the key lock is unlocked the alarm bell may be started or stopped After the alarm bell is start...

Страница 27: ...and both the QUERY indicator and the indicator of the queried content will flash If QUERY TIME is pressed the upper nixie tube will display the year month day and code of the information If QUERY is p...

Страница 28: ...in the format of After BWD key S10 is pressed the figure displayed by the nixie tube will increase within the range of 1 60 in a cyclic way 2 If Switching key S12 is pressed again the nixie tube will...

Отзывы: