05-201133_13-0D

05-201133_13-0D

6. SECURE BASE FEET:

A. Depending on the model purchased, your base feet will 

either fit onto the outside of the leg pole, or slide into the 

bottom of the leg pole. 

B. After installing the base feet, line up the holes in the leg to 

the holes in the feet and secure with the hardware indicated 

in Detail G.

7. INSTALL AUGER ANCHORS:

A. Anchors must be placed inside shelter. Start at the corners 

of the shelter. insert a ¾” pipe or steel rod, through the eyelet 

of the auger and screw the anchor into the ground. (if ground is 

too hard, dig a hole with a shovel or post hole tool.)    

OPTIONAL:

 

Fill with cement.

B. Space out the remaining anchors evenly along the length of 

the shelter. Screw the anchor into the ground until the eyelet is 

sticking out of the ground by 1-2” so it can be anchored to the 

legs. 
 C. Wrap the cable provided through the eyelet of the anchor 

and around the frame as indicated in Detail H. Secure the cable 

with the clamps provided.
D. Repeat for middle legs by attaching cable around foot plates.

8. zIPPER DOOR AND OR END PANEL INSTALLATION:

Secure 

with bolt 

and nut

DETAIL G

DETAIL H

A. Hold the end panel at the top center with the white inner 

surface facing the inside of the shelter (if you have a white 

shelter the inner surface has the visible weld seams).
B. Unscrew top rail from the top bend and place the webbing 

 in between. The top rail should pass through the loop of the 

webbing. Reconnect top rail onto rib and secure it with the 

screws indicated. See Detail i.
C. Remove the nut from the side rail and carefully pull 

the side rail away from the 

ShelterLock

 (pull away only 

enough to pass the webbing through the connection). 

If 

this connection has the wind brace on it remove the 

wind brace end before pulling the side rail.

 Replace the 

cross rail and wind brace. See Detail j. Replace the nut and 

tighten. Repeat this on the other side.
D. At the bottom, where the webbing exits the pocket on 

each side of end panel, pull webbing to remove the slack.  

Be careful not to pull the webbing through the other side of 

the panel. 
e. install the “S”- hook from the ratchet into the leg of the 

shelter.  insert the webbing into the spindle of the ratchet 

and pull tight. See Detail j. Wind the ratchet so that the web-

bing overlaps itself. Repeat this process on the other side of 

the panel. Position the end panel so that it is centered on the 

building. 
f. Tighten the ratchets, alternating from one side to the other, 

until the end panel is tight. Repeat these steps on the other 

end of the building. 

DETAIL I

Slits

Slit in fabric 

folded around 

frame and 

cross rails 

inserted 

through slits

INSIDE vIEw

SIDE vIEw

DETAIL J

9. INSTALLING THE COVER ON THE FRAME:

A. Lay the cover on the ground next to the 

frame with the inside of the cover (the side with 

the pipe pockets) facing down and the webbing 

on the front and rear of the corner of the build-

ing. Position the cover so that it is centered on 

the frame, front to back. See Detail K.
B. fold over the side so the pipe pocket is now 

accessible. insert a cover pipe into the pipe 

pocket slot, at the first middle rib from the front 

and the first middle rib from the rear. Some of 

the pipe will be exposed. for long buildings it 

may be necessary to use additional pipes in the 

middle. See Detail L. Remove pocket pipe to 

install later.
C. Tie the rope on each of the exposed pipes 

and throw the other end of the rope over the 

frame. See Detail M.
D. Move to the other side of the frame and pull 

the cover over the frame with the rope. This 

 may require two or more people. See Detail N. 

Check that the Logo reads upright as shown.

DETAIL K

DETAIL L

DETAIL M

DETAIL N

END PANELS 

NOT SHOwN 

FOR CLARITY

10114

01010

Содержание Round Top

Страница 1: ...l Safety Glasses Rope Tape Measure Ratchet with Socket Set Adjustable Wrench Step Ladder Rubber Mallet Utility Knife 5 8 Concrete Drill Bit Sledge Hammer 05 201133_13 0D 05 201133_13 0D ShelterLogic L...

Страница 2: ...could shed snow ice or excessive run off onto your shelter DO NOT hang objects from the roof or support cables Do not smoke or use open flame devices in or around the shelter DO NOT store flammable l...

Страница 3: ...d instructions completely before assembly Layout out frame parts as shown and match up items with quantity to make sure no parts are missing ShelterLogic LLC 150 Callender Road Watertown CT 06795 www...

Страница 4: ...3 Bolt 2 Bolt 3 Install Side Rails and ShelterLock Stabilizer Blocks A Place assembled first end rib in the staked area Place the ShelterLock on the upright as shown in Detail D From the outside of t...

Страница 5: ...d brace end before pulling the side rail Replace the cross rail and wind brace See Detail J Replace the nut and tighten Repeat this on the other side D At the bottom where the webbing exits the pocket...

Страница 6: ...fit in bottom pocket of door Slide pipes into one another to assemble NOTE If your model included a roll up door kit follow the instructions below Read all instructions before beginning assembly DOOR...

Страница 7: ...u AVERTISSEMENT Avant d installer consulter tous les codes locaux et municipaux concernant l installation d abris temporaires Choisir soigneusement l emplacement de l abri Faire attention aux lignes l...

Страница 8: ...ature de bout Renfort contre vent le nombre de partie de la fabrication le Nombre de r f rence d assembl e 1 2 3 4 5 6 7 8 10224 10225 10226 10273 02030 02031 10110 10111 9 10 11 12 13 14 15 16 10112...

Страница 9: ...s 10210 3 Boulons 2 Boulons 3 Installer les barres transversales et les bloques stabilisateur ShelterLock A Positionner la premi re ossature assembl e dans l emplacement pr vu Placer le Shelterlock en...

Страница 10: ...s des poteaux et s curisez avec la quincaillerie indiqu e dans le d tail G 7 Installation des ancres A Les ancres doivent tre placer l int rieur de l abris Com mencez au coins de l abris Ins rez une b...

Страница 11: ...rture de porte suiver les instructions si des sous S assurer de bien lire les instructions avant de commencer l assemblage LE KIT D OUVERTURE INCLUSE 2 Crochets en S 2 Bouchons pour les tuyaux 1 Croch...

Страница 12: ...o La cubierta puede limpiarse f cilmente con jab n suave y agua ADVERTENCIA Antes de la instalaci n consulte la normativa local y municipal relativa a la instalaci n de cobertizos tempora les Elija la...

Страница 13: ...laje LLAME a nuestro Dpto de Servicio al Cliente 1 800 524 9970 CANADA 1 800 559 6175 atenci n NO DEVUELVA EL PRODUCTO AL DISTRIBUIDOR Para las piezas faltantes el reemplazo o la asistencia con el ens...

Страница 14: ...os bloques estabilizadores ShelterLock A Coloque la cercha terminal que ensambl primero en el rea con estacas Coloque ShelterLock en el paral como se ilustra en la figura detallada D Desde la parte ex...

Страница 15: ...ado del tejido del frente y posterior de la esquina de la unidad Coloque la cubierta de modo que est centrada en la estructura desde el frente hacia atr s Refi rase a la figura detallada K B Doble el...

Страница 16: ...Si su modelo inclu a un kit de puerta enrollable siga estas instrucciones Lea todas las instrucciones antes de comenzar el ensamblaje EL KIT DE PUERTA INCLUYE 2 Ganchos en S 2 Conectores para postes 1...