Segen Solar EPM Plus 5G Скачать руководство пользователя страница 7

AN_EPM_SOL_Ver0.

 

Setting: Backflow Work Mode 

 

Mode 2 is always recommended for unbalanced loads. (for detailed explanation refer to the user 
manual. 

After adjusting the settings successfully

, check on the advanced info menu option for the 

following. 

 

Inverter Power

: This will display the power of each inverter as measured by the EPM 

 

CT  Connect  Status: 

This must show OK, otherwise if CT_NG is displayed it means that the CT is 

open circuit or current passing through is extremely low which is usually a result of using CTs with 
a secondary current less than the recommended 5A. 

 
 

Checking your CT polarity 

 

The physical check is to make sure that P1 always faces the grid and P2 always faces the load.  

If in 

doubt 

about the direction

 of the 

CT,

 

please follow these steps to double check. 

On your inverter menu, navigate to Advanced Settings and on the Grid ON/OFF select off. 

 
 

 

 

Off  state  stops  the  inverter  from  producing  power.  (Must  remember  to  switch  Grid  back  on  after 
check) 

 

Navigate to the Advanced info and check the power of the individual phases. Note at this stage 
only your grid is available and producing power. 

 

The  individual  phases:  Active_APwr,  Active_BPower  &  Active_CPower  will  show  -(negative)  Watts 
showing that you are buying power from the grid, once all 3 phases are verified, navigate back to 
Advanced Settings and switch grid on. 

 

 
 

Содержание EPM Plus 5G

Страница 1: ...Application Note Solis and EPM Quick Setup Guide...

Страница 2: ...wires between the inverter and EPM are properly connected asin the manual refer to system wiring diagram The EPM should always be connected to the first inverter on the RS485 bus if multiple units ar...

Страница 3: ...d Inverter communicates with Modbus protocol via RS485 2 wire UTP FTP Twisted pair cableshould always be used Important Settings for Inverter and EPM For the EPM to work the settings and parameters to...

Страница 4: ...rity onthe individual phases The image below shows the EPM landing page Advanced Settings Access the menu by pressing the Enter key and navigate to Advanced settings using the down arrow Press Enter o...

Страница 5: ...the set value NB For zero export plants it is important to note that in case of a large sudden drop in load there will be a momentary export of power if there is no buffer So for plants where prepaid...

Страница 6: ...atio is obtained by dividing the Primary Current Secondary Current e g a 200 5 CT will be 0040 1 Setting FailSafe Must be set to run This is a safety feature that stops inverter production should the...

Страница 7: ...mended 5A Checking your CT polarity The physical check is to make sure that P1 always faces the grid and P2 always faces the load If in doubt about the direction of the CT please follow these steps to...

Страница 8: ...er for details on how to connect the plant to the internet for remote monitoring andcreating an account for cloud monitoring NB Remote monitoring data is not real time Data points are logged after eve...