Lyve Rack R1 Installation Guide
34
8 | Turn ON power
Note
Please ensure that all equipment is connected to the appropriate power sources
before starting the powering ON sequence.
8.1 | Switch ON storage enclosure
To switch ON the 5U84 storage enclosure:
•
Switch ON the power on both PSUs using Power Switches (see
).
Note
It is not required to switch ON both PSUs simultaneously. However, it is
recommended to switch ON PSU 0 followed by PSU 1.
Figure 16: 5U84 storage enclosure PSU. Power switch 'O' = OFF; 'I' = ON
Wait for five minutes to complete initialization and self-test functions. Then verify that the 5U84
storage enclosure front panel LEDs are illuminated as shown in