Lyve Rack R1 Installation Guide
14
a.
Ensure anti-temper locks of the top drawer are unlocked using the supplied T20
screwdriver.
b.
Using drawer latches, push both latches of the same drawer towards the center of the
drawer.
c.
Slowly pull top drawer towards yourself.
d.
Insert all DDICs starting from top drawer with drives at the front left of each row leaving
no empty drive slots paying attention to inserting drives in ascending order.
e.
Repeat until all rows on the top drawer are full. Visually re-check that the DDIC sequence
numbers match the figure.
f.
Close the drawer and lock it.
g.
Repeat the steps a through f for the bottom drawer.
Figure 7: Populated the top drawer
Populate the top drawer first. Close and lock the
drawer.
Figure 8: Populated the bottom drawer
Populate the bottom drawer after filling and
closing the top drawer. Close and lock the
drawer.
8.
The anti-tamper locks do not have to be used. If they are used to lock the drawer, store the T20
screwdriver safely afterwards. Now that all DDIC and rear modules are inserted, the rack
installation can progress to the next stage.
5.4 | Server installation
Depending upon your server configuration, follow instructions provided in the Server Installation
chapter of
S
UPERMICRO
S
UPER
S
ERVER
U
SER MANUAL
6019P-WTR
OR
S
UPERMICRO
S
UPER
S
ERVER
U
SER MANUAL
6019U-TRT
to
unpack and install the servers into the rack.
Refer to
above. The servers are not configured identically. Hence, you must first identify
server B box and rack the server directly above the 5U84 storage enclosure. After racking server B,
identify server A box, and rack it directly above server B.