FOR THE INSTALLER: Location & Assembly
Location:
After uncrating and inspection, the unit is ready for
installation. It is important that the machine be
installed in a location where it has enough space
around it to be accessible for service. A minimum
of 6" must be allowed at the back for air circulation
on air cooled models. Try to avoid hot, dirty and
crowded locations. Be sure that the location for the
machine is within the envrionmental limitations.
Storage Bin:
Tip the storage bin on its back, using parts of the
carton to protect the exterior finish. Install the
casters, use a heavy duty leg kit if stacking two ice
machines on one bin.
1. Arrange for proper electric, water and drain.
See instructions for the plumber and for the
electrician.
2. Single ice machine on bin: Use caster kit KBC9.
After mounting the casters, position the ice storage
bin in the selected location:
Two ice machines on a bin require stacking kit
KSMCM48. Do NOT use casters on units with two
ice machines on one bin.
Note: Allow enough space to the left and back to
service the machine. Do NOT push the bin into
postion, instead, lift it there. Pushing a bin may
damage the legs and leg mounts.
Level the bin in both the front to rear and side to
side directions by adjusting the casters. Stacked
units use non-adjustable legs, and must be leveled
with shims. Select a well ventilated location for air
cooled models.
Note: Air cooled models blow air from front to back.
3. Inspect the bin top mounting gasket which
should be flat, with no wrinkles, to provide a good
water seal when the cuber is installed on top of the
bin.
4. Install the bin bumpers onto the top edge of the
bin, so that they hang-over the back.
Ice Maker:
Install the modular cuber on top of the bin using
care to be sure a good seal is made between the
two cabinets. Use of a mechancial lift is
recommended. Align the holes in the bottom rear
of the cabinet to mate with the two mounting holes
on the top rear of the bin.
Use bolts and straps found on the back of the
icemaker to secure the ice machine to the bin.
When alignment and leveling are completed,
tighten the bolts to secure the mounting straps.
Remove the front panels, and remove the
evaporator shipping brackets and hardware.
SHIPPING
BRACKETS
ICE MACHINE AND BIN ASSEMBLY
MCM1462
April, 1993
Page 3