MOUNTING INSTRUCTIONS
Страница 1: ...FixGrid18 100 MOUNTING INSTRUCTIONS...
Страница 2: ...ning of your solar plant from the Schletter configurator Risk of breakage PV modules can be damaged if they are stepped on Planning of the solar power system installation and commissioning may only be...
Страница 3: ...cific rules and regulations have to be observed Roof cleaning In order to ensure that the base rails are supported across their entire surface impurities such as moss leaves dirt stones etc have to be...
Страница 4: ...n mounting frames with the module supports Defining the base rail lengths and distances between module supports maintenance walk way width Distance a has to be adapted according to the width of the ma...
Страница 5: ...s Take into account a projection of the surface protection mat of at least 30 mm at the rail ends In the case of transversely flowing rainwater the distance has to be dimensioned on the basis of the a...
Страница 6: ...ansversely draining roof water The permissible surface pressure of the roof has to be checked Sufficient drainage of rainwater has to be ensured Align base rails parallel to each other align the FixZ...
Страница 7: ...to the alignment of the module row Apply the Rapid 16 end clamps at the top and at the bottom to the module and tighten Screws M8 T40 Place the module center clamp on the module do not tighten Connect...
Страница 8: ...the base rails see Detail A Ballasting with additional trough see Detail B Ballasting with additional ballast shafts see Detail C Ballasting from the combination of the 3 possibilities The informatio...
Страница 9: ...are turned 180 degrees recesses on the left from right to left The tray always lies with the side of the slots at the bottom and in the base rail with a positive fit At the last ballast tray the end h...
Страница 10: ...0 0 SCHLETTER SOLAR GMBH Alustrasse 1 83527 Kirchdorf GERMANY www schletter group com We reserve the right to changes including technical modification 10...