background image

 

 

 

Terminal board for environmental sensors 

Cable-gland for environmental sensors 

DIP-switch for the configuration of environmental 
sensors 

o

  Connect  RS-485  comms cable to terminals M1  and M2 (in-out connection)  to  ES977  board  by 

using a “Belden 3106A Paired EIA Industrial RS-485 PLTC/CM” cable and fasten the cable braiding 
to the copper cable glands. 

o

  Set  up the rotary  switches for Modbus  address  on  ES1004  board and DIP-switch SW1 for 

termination enable/disable on ES977 board. 

 

 

 

M1 

RS-485 IN 

M2 

RS-485 OUT 

RS-485 fuses 

Rotary-switch 
Modbus address 
strings 1-8 

Rotary-switch 
Modbus address 
strings 9-16 

SW1 

Termination DIP-
switch 

  Connect the strings. 

o

 

Open the disconnect switch, open the fuse-holders

, close the string box cover. 

o

  Plug the contacts. Pull connectors to check that plugging is correct. 

 

 

 

Connection of string positive pole 

Connection of string negative pole 

Positive pole fuses, strings 1-8 

Negative pole fuses, strings 9-16 

Negative pole fuses, strings 1-8 

Negative pole fuses, strings 9-16 

 

 

Содержание 15W00EPBA410

Страница 1: ...the Installation Guide carefully before operating the SMART STRING BOX LT products KEY TO SYMBOLS DANGER Indicates an operating procedure which if not carried out correctly may lead to injuries or ev...

Страница 2: ...he strings by operating inside the product or on strings connected to the product It is forbidden to make any technical or mechanical modifications to the product even when out of warranty DANGER Deat...

Страница 3: ...ctly forbidden to proceed with product handling and assembly operations in adverse weather conditions in snow rain or persistent fog Always check that there is no water or condensate inside the produc...

Страница 4: ...ed to the same inverter Open the cover of the SMART STRING BOX LT and open the disconnector it is NOT necessary to remove the polycarbonate panel Disconnect all the strings from the SMART STRING BOX L...

Страница 5: ...ained o Insert the functional earth cable through the dedicated cable lug o Connect the functional earth cable to the relevant terminal o Reassemble the polycarbonate panel by pressing it and tighteni...

Страница 6: ...4 board and DIP switch SW1 for termination enable disable on ES977 board M1 RS 485 IN M2 RS 485 OUT F RS 485 fuses A Rotary switch Modbus address strings 1 8 B Rotary switch Modbus address strings 9 1...

Страница 7: ...ach string on the connection screws of each fuse holder Voltage must be positive unless strings are in the shadow Extract or insert the fuse into the fuse holder DANGER Check with a current probe that...

Страница 8: ...than generally indicated UNINSTALLING THE PRODUCT Carry out the PRELIMINARY SAFETY OPERATIONS Remove the polycarbonate panel and make sure that no voltage is applied between 230 V auxiliary voltage te...

Страница 9: ...ili su santerno com Si raccomanda la lettura dell intera Guida all Installazione prima dell uso delle SMART STRING BOX LT SIMBOLOGIA PERICOLO Indica procedure operative che se non eseguite correttamen...

Страница 10: ...stringhe operando all interno del Prodotto o sulle stringhe ancora connesse al prodotto vietata qualunque modifica elettrica o meccanica interna anche fuori dal periodo di garanzia PERICOLO Pericolo d...

Страница 11: ...450 120 DIVIETO vietato procedere alle operazioni di movimentazione e montaggio del prodotto in condizioni meteo avverse presenza di neve pioggia nebbia persistente Verificare in ogni caso l assenza d...

Страница 12: ...tte le cassette stringa connesse allo stesso inverter Aprire la portella della SMART STRING BOX LT e aprire il sezionatore NON necessario rimuovere la lastra in policarbonato di protezione Scollegare...

Страница 13: ...lla terra funzionale attraverso il pressacavo dedicato o Connettere il cavo della terra funzionale al relativo morsetto o Rimontare il policarbonato di protezione premendo sul policarbonato per inseri...

Страница 14: ...sinserimento della terminazione su scheda ES977 M1 RS 485 IN M2 RS 485 OUT F Fusibili RS 485 A Rotary switch indirizzo Modbus stringhe 1 8 B Rotary switch indirizzo Modbus stringhe 9 16 SW1 DIP switch...

Страница 15: ...ibile Le stringhe devono presentare tensioni positive e simili a meno di ombreggiature Estrarre o inserire il fusibile dal portafusibile PERICOLO L apertura e la chiusura dei portafusibili non pu avve...

Страница 16: ...to a quanto prescritto DISINSTALLAZIONE Eseguire le OPERAZIONI PRELIMINARI DI MESSA IN SICUREZZA Verificare l assenza di tensione tra i morsetti di alimentazione ausiliaria 230 V tra il polo positivo...

Отзывы: