656-500
Handling
The dimensions and weight of each section of the PureWave AVC are
listed in Table 1. Each section can be lifted using an overhead crane
or a forklift.
If an overhead crane is to be used:
1. Use 8-foot or longer hoist slings of equal length to prevent dam-
aging the enclosure during lifting.
2. Arrange the hoist slings so as to distribute the lifting forces
equally between the eyebolts.
3. If hoist slings or chains have been provided—match the letter
tag on each sling hook to the corresponding letter tag on each
eye-bolt on the roof of the section. See Figures 1 and 2.
4. Make sure that the lifting hooks are completely engaged in the
eyebolts before lifting the enclosure. Do not cross the slings or
chains.
5. Avoid sudden starts or stops.
If a forklift is to be used, engage the forks fully across the span of
the wooden pallet mounted to the base of the section.
If the PureWave AVC is to be transported through a building, place
roller dollies under each corner of the section
Ç
WARNING
When handling a PureWave AVC with an overhead hoist, observe
standard lifting practices as well as the general instructions below.
Failure to follow these precautions can result in serious per-
sonal injury or equipment damage.
INSPECTION AND HANDLING
Figure 1. Sling hooks with letter tags.
Figure 2. Section ready to lift.
Содержание PureWave AVC
Страница 24: ...Printed in U S A...