Generating Reports

The 

Report 

feature can be used to save the control 

software settings and stored data to a computer as a CSV 
(comma-separated value) file. The report can be kept as a 
permanent record and the report data used in spreadsheets 
or other types of programs.

Complete the following steps to generate report:

STEP  1.  

Connect a portable computer to the control and 
start the IntelliLink software.

For details, see the “To Start the IntelliLink 

Software” section in Instruction Sheet 1011-530, 
“BankGuard Plus Control: 

Setup

.” If the com-

puter is already connected to the control, this 
step can be skipped.

STEP  2.  

From the 

Data

 menu, choose the 

Reports 

option.

STEP  3.  

In the dialog box, select the type of report to 
generate, and then click on the 

OK

 button.

There are four types of reports:

Full

.

 

Includes all the information contained 

in the control

System Setup and Operation

. Contains the 

configuration data for the control

Troubleshooting Information

. Contains 

the information recorded in the troubleshoot-
ing logs

Historical Data

. Contains the daily statis-

tics, the potential device profiles, the switching 
data, and the log of power outages

STEP  4.  

In the Save Report dialog box, specify a name 
and location for this report, and then click on 
the 

OK 

button..

If a location is not specified, the file is saved 

to the same directory as the program files for 
this for this type of control. The extension “.CSV” 
is added automatically.

When the report is complete, the message 

“Task completed” appears on the status line of 
the Writing Report dialog box.

Содержание BankGuard PLUS

Страница 1: ...eplate 5 Control Software 6 SCADA Communication Equipment 6 Control Operation Overvoltage Protection for Capacitor Banks 7 Protection for Reactors 7 Automatic Control Features 8 Ungrounded and Grounde...

Страница 2: ...retrieve and refer to this publication Proper Application WARNING The equipment in this publication is only intended for specific application The application must be within the ratings furnished for...

Страница 3: ...ecautions are not followed NOTICE NOTICE identifies important procedures or requirements that can result in product or property damage if instructions are not followed Following Safety Instructions If...

Страница 4: ...ed only to Qualified Persons See the Qualified Persons section on page 2 2 SAFETY PROCEDURES Always follow safe operating procedures and rules Always maintain proper clearance from energized component...

Страница 5: ...essible during regular operation and troubleshooting The BankGuard Plus Control faceplate includes LEDs and buttons for monitoring the capacitor bank reactor and the control It also includes an LCD sc...

Страница 6: ...ck perpetual calendar integrated circuit devices are battery backed and have a 10 year battery life in the Non Powered state The real time clock perpetual calendar integrated circuit counts seconds mi...

Страница 7: ...Figure 2 This curve applies for up to 300 applications of power frequency overvoltages of the magnitude and duration shown The standard further requires that capacitors be capable of continuous opera...

Страница 8: ...than the normal lockout process This logic is activated after a field adjustable time delay of 0 2 to 5 seconds by such faults producing a capacitor bank neutral to ground voltage in excess of an adj...

Страница 9: ...wye banks the control uses an ana log input and digital voltmeter to detect the capacitor bank neutral to ground voltage as monitored by an S C 15 Volt Ampere Potential Device A digital filter attenu...

Страница 10: ...utral to ground voltage magnitude to the Gross Over Voltage Level Lockout Level and Alarm Level setpoint values if enabled If the compensated neutral to ground voltage magnitude exceeds a setpoint val...

Страница 11: ...ded In addition to the neutral to ground potential device one 30 Volt Ampere S C Potential Device is required to be installed on any one of the line phases to obtain a reference angle when the Unbalan...

Страница 12: ...ue continuously for a time greater than the applicable time delay setpoint value the appropriate control action is taken The control will lock out the bank if the Gross Over Voltage Level or the Locko...

Страница 13: ...rovided in addition to capacitor unit manufacturing tolerance Using the Law of Cosines a corrected magnitude is obtained See Figure 8 A cor rected magnitude is calculated and stored in the control s m...

Страница 14: ...g the stored approximate corrected magnitude is subtracted from the real time tap point to ground voltages magnitude in percent during each 200 milliseconds to obtain a compensated neutral to ground v...

Страница 15: ...option STEP 3 In the dialog box select the type of report to generate and then click on the OK button There are four types of reports Full Includes all the information contained in the control System...

Страница 16: ...program files for this for this type of control The extension CFG is added automatically Note This process does not save the Location setting on the Setup screen or the Communications RTU Address set...

Страница 17: ...n the Cancel button to close the Connect dialog box If the IntelliLink software is already run ning choose the Disconnect option from the Connection menu and then choose the Close Screenset option fro...

Страница 18: ...reenset from memory STEP 2 FromtheFilemenu choosetheOpenSnapshot option The Open Controller Data File dialog box opens STEP 3 Select the snapshot desired to use and then click on the Open button STEP...

Страница 19: ...ndows choose Start menu Programs EnergyLine Update The Update window appears Figure 10 b Select the desired options and then click on the Start Update button Note If the control is not connected to CO...

Отзывы: