8.
WRAPPING MACHINE OPERATION
8.1.
Installing the film
Place the film roll on the feeder pin in the following order (see diagram:
Deflect the support with the metal rollers and secure it using the hook attached to the wrapping
assembly.
Using a lever (crank) undo the upper pin pressing the film upwards.
Set the height of the lower pin in position appropriate for the film roll width (1' 8" or 2' 5").
Place the film roll on the lower conic pin.
Clamp the roll by turning the lever (crank) on the upper pin so that the roll is securely held in
the vertical position.
Protect the roll from unscrewing using the nut on the crank screw.
When installing the roll of film, place its internal sticky side towards the bale axis.
Properly set the initial tightening of the film (Punkt 8.4).
Pull the film through the rubber rollers as indicated on the diagram located on the gear cover.
Pull the end of the film so that it may be easily handled in the machine.
The wrapping machine is pre-set to use 1' 8" film. To use 2' 5" film, the chain wheel must be
replaced (Fig. 22). To do so, it is required to:
Unscrew the 4 M12 hub nuts, remove the side cover of the rotating frame (on the side of the
chain transmission),
Loosen the M12 screw on the chain tightening mechanism,
Remove the chain from the Z17 chain wheel installed on the main shaft and remove the split pin
securing the wheel,
Remove the Z17 chain wheel form the shaft (using an appropriate tool),
Secure the removed Z 17 chain wheel,
Replace it with a Z27 chain wheel,
Secure the Z27 repeating the above procedur
ę
in the reverse order.