Salamander Pumps AccuBoost Series Скачать руководство пользователя страница 15

13

7. Final Commissioning

-  Flush all air from pipework before connecting AccuBoost unit
-  Connect AccuBoost unit to pipework
-  Close all outlets and ensure isolation valve(s) are open to and from the AccuBoost
-  Turn on stopcock to begin filling the vessel
-  Turn on the electrical supply to the pump (if applicable). The pump will begin to run to help  

  fill the vessel
-  Open each outlet that is supplied by the AccuBoost system until all air has been expelled
-  Close all outlets and allow the vessel to fully fill. The fill time of the vessel depends on  

  the mains water flow and also the size of the vessel
-  The pump (if applicable) will continue to run even when all outlets are closed, until the  

  vessel is full and the correct system pressure has been reached
-  The AccuBoost (including pump if applicable) and all system pipework should be checked  

  for leaks whilst the vessel is filling, when the vessel is full and while water is being drawn  

  from an outlet. Any leaks should be rectified and then the checks performed until no leaks  

  are present.
Note: The pump responds to the pressure within the system. When the system pressure drops 

below the pre-programmed level due to an open outlet, it will automatically turn on. If a small 

amount of water is drawn from the system that does not allow the pressure to drop below 

the pre-programmed level, the pump will not turn on. When outlets are closed the pump will 

continue to run until the vessel has filled to the correct pressure. 

If you have any queries regarding the installation of AccuBoost please call PumpWise on 

0191 516 2002

It is critical to discharge water through the pump into a container using natural flow before 

connecting the outlet of the pump to the pipework. This ensures the air has been discharged 

from the inlet pipe work and pump chambers. The best method is :- 
-  Connect the inlet pipework to the inlet anti-vibration hose
-  Check that all isolating valves on anti-vibration hoses are open
-  Turn on stopcock and allow water to flow from the pump outlet anti-vibration hose into a  

  suitable container (such as a bucket)
-  Turn off the stopcock and connect the pump outlet anti-vibration hose to the pipework
  DO NOT RUN PUMP DRY- to do so will cause irrepairable damage to your pump and will  

  invalidate your warranty

Priming (pumped versions only)

For all units

Содержание AccuBoost Series

Страница 1: ...Installation and warranty guide for AccuBoost range ISSUE 2 0 OCT 2019...

Страница 2: ...ctrical Regulations Building Regulations and local byelaws Correct installation is the guarantee of safety and a trouble free system It is therefore important to read these instructions thoroughly and...

Страница 3: ...1 Location 6 2 Water Temperature 6 3 Pipework 6 4 System Connections 6 5 Air Precharge Pressure of the Vessel 6 6 Electrical Installation pumped versions only 7 Final Commissioning 13 8 AccuBoost Comp...

Страница 4: ...s been depleted the flow will continue at the natural mains unassisted flow rate Pumped Units For applications where the flow rate and or the pressure of the incoming mains water is low below 12 L min...

Страница 5: ...aintenance both water and electrical Ensure the surface where the unit is installed is capable of supporting the maximum weight of the unit Fit a double check valve and pressure regulator where approp...

Страница 6: ...s Pumped Combi Boiler Outlets Recommended upstream plumbing not supplied Maintenance bypass isolating valves not supplied Double check valve Pressure reducing valve Stop cock Unpumped Combi Boiler Out...

Страница 7: ...plumbing not supplied Maintenance bypass isolating valves not supplied Double check valve Pressure reducing valve Stop cock Unvented Cylinder Outlets Note In all instances the installation must compl...

Страница 8: ...ain to the AccuBoost unit should be kept as short as possible Longer pipe runs may impact on the performance of the unit The isolating valves on the supplied anti vibration hoses should be accessible...

Страница 9: ...um of 4 C The cold water should be stored and distributed below 20 C to prevent Legionella growth 6 2 Water temperature Ventilation Ensure adequate airflow to cool the motor Ideally leave 100mm air ga...

Страница 10: ...equirements of the water supply water fittings regulations a type EC verifiable double check valve should be fitted Refer to Figures 1 4 on page 4 5 Ensure the combined mains pressure and pump pressur...

Страница 11: ...vibration hoses should be used to make the connections between the pipework and AccuBoost unit The supplied flat washers should be used when attaching the hoses The hoses should be finger tight plus...

Страница 12: ...ains water static pressure when no outlets are drawing water to be measured and the air precharge in the vessel adjusted accordingly Refer to the following steps and Table 1 Checking air precharge pre...

Страница 13: ...checked during the process to ensure the required air pressure is not exceeded Mains Static Pressure Correct Air Precharge Pressure of Vessel Pressure Differential Pressure Reducing Valve Maximum Set...

Страница 14: ...supply cable If the unit is to be installed in a loft garage outbuilding or other location where there is a risk of water ingress or condensation to the socket an appropriately IP rated socket must be...

Страница 15: ...ds to the pressure within the system When the system pressure drops below the pre programmed level due to an open outlet it will automatically turn on If a small amount of water is drawn from the syst...

Страница 16: ...ple Pumped example Figure 10 Figure 11 vessel air precharge valve cover brass inlet outlet connection base front view side view vessel air precharge valve cover inlet connection base outlet connection...

Страница 17: ...em water pressure by opening an outlet tap and allow the vessel to fully empty 4 Unscrew the inline strainer filter cover some residual water may be released when cover is unscrewed 5 Remove the filte...

Страница 18: ...ictor Colour Total Output Flow 60 litre 2 L min green 14 L min 120 litre 4 L min pink 16 L min 180 litre 6 L min grey 18 L min 300 litre 18 L min brown 30 L min 450 litre not restricted n a 36 L min T...

Страница 19: ...vessel connector Note a pumped unit should be installed after the stopcock and before any outlets Any outlets between the stopcock and the AccuBoost pump will not benefit from the AccuBoost unit If t...

Страница 20: ...ystem should be set to the same value Please see typical installation examples below 11 Multiple Vessels Figure 18 Figure 19 Note In all instances the installation must comply with the latest water el...

Страница 21: ...m water pressure by opening an outlet tap and allow the vessel to fully empty 3 Disconnect the vessel hose from the pump vessel port 4 Attach the captive nut of the brass connector from the connector...

Страница 22: ...SSYACCUFORCE Mechanical seal Nitrile carbon ceramic Pump body impeller Brass Enclosure protection IPX2 Motor Type Capacitor start and run induction motor Duty rating Continuous Electrical Power supply...

Страница 23: ...ble 4 Note quoted values may vary due to tolerances and site conditions 13 WEEE Directive Your appliance contains valuable materials which could be recovered or recycled At the end of the product s us...

Страница 24: ...to drop within the system Reduced intermittent flow Insufficient natural mains flow no water see above Blocked filters Ensure all filters are free from debris Anti vibration couplers restricting flow...

Страница 25: ...no obligation whatsoever under this Warranty to repair or replace equipment which has been misused tampered with or modified altered in any way without the consent in writing from the Company or if an...

Страница 26: ...assignee or subsequent purchaser of the equipment c You must evidence the date of purchase by retaining the original invoice from the dealer Without such evidence the Company reserves the right to re...

Страница 27: ...his Warranty a visit from a Salamander service engineer may be necessary Engineer visits are not covered under part of the warranty agreement In circumstances where in the opinion of the Company the d...

Страница 28: ...er your warranty Apply online at www salamanderpumps co uk Apply by phone 0191 516 2002 Unit 2c Colima Avenue Enterprise Park West Sunderland SR5 3XE Get in touch we re here to help call us on 0191 51...

Отзывы: