Digging the Hole
•
Position the machine over the
desired hole replacement area.
Extending boom 12 or 14
inches and allowing enough
slack in rope to drill a straight
hole down.
•
Turn on the remote and toggle
the Auger switch to the correct
direction then lower the auger
to begin digging.
•
NOTE:
It may be required to
lower the auger speed to allow
for booming down of the digger
derrick while digging.
•
CAUTION: Buried lines may
be in your digging area.
Содержание EZ Hauler 4100
Страница 1: ...EZ Hauler 4100 Training Procedure Manual...
Страница 4: ...Hard hats and protective gear must be worn by all personnel when using the EZ Hauler 4100...
Страница 9: ...Pre trip Inspection Check all tires on the EZ Hauler 4100 trailer for wear proper inflation...
Страница 12: ...Pre trip Inspection Turn on the remote control check the function of all controls...
Страница 29: ...Auger Operation Procedure...
Страница 31: ...3 Release auger latch and slowly lower auger 4 IMPORTANT You must raise boom to lower auger assembly...
Страница 32: ...5 Carefully unwind dig auger and remove strap You are now ready to use the remote control to auger as needed...
Страница 41: ...Bucket Assembly Standard Operating Procedure...
Страница 45: ...Shows the bucket mount installed and pinned it in place...
Страница 46: ...The bucket can now be mounted to either side of the mount to best accommodate working from it...
Страница 49: ...Hydraulic Pole Guide Procedure...
Страница 50: ...1 Slide pole guide in to receiver of sheave head 2 Install and secure pin...